TUPP094 Recent Progress of Beam Commissioning at J-PARC Linac 646
 
  • T. Maruta
    J-PARC, KEK & JAEA, Ibaraki-ken, Japan
  • K. Futatsukawa, T. Miyao
    KEK, Ibaraki, Japan
  • M. Ikegami
    FRIB, East Lansing, Michigan, USA
  • Y. Liu
    KEK/JAEA, Ibaraki-Ken, Japan
  • A. Miura, H. Sako
    JAEA/J-PARC, Tokai-Mura, Naka-Gun, Ibaraki-Ken, Japan
 
  We installed Annular-type Coupled Structure (ACS) linac in year 2013 in present linac downstream to extend the beam energy from 181 to 400 MeV. The beam commissioning had been conducted for one month in last December to January, and then we successfully extract 400 MeV beam. Whereas, we stably operate the linac at peak current of 15 mA, which is equivalent to 300 kW at the extraction of 3 GeV RCS, we observe unexpected residual radiations in ACS section. In this presentation, we review the recent progress in beam commissioning and beam loss study.  
 
THPP091 Installation and Performance Check of Beam Monitors for Energy Upgraded J-PARC Linac 1059
 
  • A. Miura, K. Hasegawa, H. Oguri, N. Ouchi
    JAEA/J-PARC, Tokai-mura, Japan
  • M. Ikegami
    FRIB, East Lansing, Michigan, USA
  • Y. Liu
    KEK/JAEA, Ibaraki-Ken, Japan
  • T. Maruta
    J-PARC, KEK & JAEA, Ibaraki-ken, Japan
  • T. Miyao
    KEK, Ibaraki, Japan
 
  An energy upgrade project has started to achieve the design beam power of 1 MW at the exit of the downstream synchrotron in the J-PARC Linac since 2009. In the upgraded project, a beam energy in the Linac has increased from present 181 MeV to 400 MeV using the additional 21 annular-ring coupled structure (ACS) cavities. The new beam monitors as the beam current monitors, the phase monitors, the beam position monitors, the transverse profile monitors (wire scanner monitors) and the longitudinal profile monitors (bunch shape monitors) for the part where the ACS cavities were installed were designed, fabricated and calibrated. Till the end of November, 2013, all beam monitors were completed to be installed. From the middle of December, we started the beam commissioning to achieve the beam energy as 400 MeV, as well as to confirm the beam monitor functioning. We achieved the 400 MeV beam acceleration at the middle of January, 2014 using newly installed beam monitors. This paper describes the beam monitor installation, calibration and the beam commissioning results of beam monitor functioning.