THPP056 | Status of the Warm Front End of PXIE | 976 |
|
||
Funding: Fermilab is operated by Fermi Research Alliance, LLC, under Contract DE-AC02-07CH11359 with the United States Department of Energy A CW-compatible, pulsed H− superconducting linac is envisaged as a possible path for upgrading Fermilab’s injection complex. To validate the concept of the front-end of such machine, a test accelerator (a.k.a. PXIE) is under construction. The warm part of this accelerator comprises a 10 mA DC, 30 keV H− ion source, a 2m-long LEBT, a 2.1 MeV CW RFQ, and a 10-m long MEBT that is capable of creating a large variety of bunch structures. The paper will report commissioning results of a partially assembled LEBT, status of RFQ manufacturing, and describe development of the MEBT, in particular, of elements of its chopping system. |
||