Author: Montesinos, E.
Paper Title Page
TUPB047 Status of the Superconducting RF Activities for the HIE ISOLDE Project 582
 
  • W. Venturini Delsolaro, L. Alberty Vieira, S. Calatroni, O. Capatina, A. D'Elia, B. Delaup, M.A. Fraser, N.M. Jecklin, Y. Kadi, P. Maesen, I. Mondino, E. Montesinos, M. Therasse, D. Valuch
    CERN, Geneva, Switzerland
 
  The planned upgrade of the REX ISOLDE facility at CERN will boost the energy of the machine from 3 MeV/u up to 10 MeV/u with beams of mass-to-charge ratio 2.5 < A/q < 4. For this purpose, a new superconducting post accelerator based on independently phased 101.28 MHz Quarter Wave Resonators (QWR) will replace part of the normal conducting Linac. The QWRs make use of the Niobium sputtering on Copper technology which was successfully applied to LEP2, LHC and to the energy upgrade of the ALPI Linac at INFN-LNL. The status of advancement of the project will be detailed, limited to the SRF activities.