A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z    

Kamitani, T.

Paper Title Page
MOP31 Development of a C-band Accelerating Module for SUPERKEKB 108
 
  • S. Ohsawa, M. Ikeda, K. Kakihara, T. Kamitani, T. Oogoe, T. Sugimura, S. Yamaguchi, K. Yokoyama
    KEK, Ibaraki
 
  High power rf processing of 1 m C-band accelerating section for Super KEKB was successfully performed and power corresponding to 42 MV/m was achieved. Processing data were accumulated including acoustic sensor to find the arcing position. No structural damage was observed from the phase shift measurement performed after the processing. Processed accelerator was installed in the beam line of KEKB linac and being re-processed. The beam acceleration of 40 MV/m was successfully achieved in October 2003. Present status of C-band accelerator development is reported.  
THP29 Development of C-band Accelerating Section for SuperKEKB 663
 
  • T. Kamitani, N. Delerue, M. Ikeda, K. Kakihara, S. Ohsawa, T. Oogoe, T. Sugimura, T. Takatomi, S. Yamaguchi, K. Yokoyama
    KEK, Ibaraki
  • Y. Hozumi
    GUAS/AS, Ibaraki
 
  For the luminosity upgrade of the present KEK B-factory to SuperKEKB, the injector linac has to increase the positron acceleration energy from 3.5 to 8.0 GeV. In order to double the acceleration field gradient from 21 to 42 MV/m, design studies on C-band accelerator module has started in 2002. First prototype 1-m long accelerating section has been fabricated based upon a design which is half scale of the present S-band section. High power test of the C-band section has been performed at a test stand and later at an accelerator module in the KEKB injector linac. In a beam acceleration test, a field gradient of 41 MV/m is achieved with 43 MW RF power from a klystron. This paper report on the recent status of the high-power test and also the development of a second prototype section.  
THP61 SKIP - A Pulse Compressor for SuperKEKB 754
 
  • T. Sugimura, M. Ikeda, K. Kakihara, T. Kamitani, S. Ohsawa, K. Yokoyama
    KEK, Ibaraki
 
  An upgrade of KEKB injector linac is planned. A main purpose of this upgrade is to increase injection energy of positrons from 3.5 GeV to 8.0 GeV for the SuperKEKB project. By a limitation of land area, our choice is to double an acceleration field utilizing a C-band accelerator structures instead of present S-band structures. Last year we developed C-band components such as accelerator structure, dummy load, 3 dB hybrid coupler, RF window, sub booster, modulator system, and so on. These components were assembled at a test stand and processed. This accelerator unit was installed in the beam line of injector linac and has been under operation. This summer we will install an RF pulse compressor system to the C-band accelerator unit. This paper reports the status of development of the RF pulse compressor system.