Ilan Shmuely (Soreq Nuclear Research Center)
TUPA172
SARAF beam commissioning results: injector, MEBT
1703
IAEC/SNRC (Israel) is constructing an accelerator facility, SARAF, for neutron production. It is based on a linac accelerating 5 mA CW deuteron and proton beam up to 40 MeV. As a first phase, IAEC constructed and operated a linac (SARAF Phase I), from which remains an ECR ion source, a Low-Energy Beam Transport (LEBT) line and a 4-rod RFQ. Since 2015, IAEC and CEA (France) are collaborating in the second phase, consisting in manufacturing of the linac. The injector control-system has been recently updated and the Medium Energy Beam Transport (MEBT) line has been installed and integrated to the infrastructure. It has been fully commissioned during the first semester of 2023 for proton and deuteron beams. This paper presents the results of the integration, tests and commissioning of the injector and MEBT.
  • J. Dumas, A. Gaget, D. Chirpaz-Cerbat, F. Gohier, F. Senee, G. Desmarchelier, N. Solenne, T. Joannem
    Commissariat à l'Energie Atomique
  • A. Perry, A. Kreisel, A. Shor, B. Kaizer, E. Reinfeld, H. Paami, H. Isakov, I. Shmuely, I. Polikarpov, I. Gertz, I. Mardor, J. Rodnizki, J. Luner, L. Weissman, N. Goldberger, N. Tamim, R. Weiss-Babai, Y. Solomon
    Soreq Nuclear Research Center
  • A. Chance, D. Darde, D. Uriot, F. Gougnaud, G. Ferrand, N. Pichoff, T. Plaisant, V. Nadot
    Commissariat à l'Energie Atomique et aux Energies Alternatives
  • T. Zchut
    Commissariat à l'énergie atomique et aux énergies alternatives
Paper: TUPA172
DOI: reference for this paper: 10.18429/JACoW-IPAC2023-TUPA172
About:  Received: 02 May 2023 — Revised: 06 Jun 2023 — Accepted: 06 Jun 2023 — Issue date: 26 Sep 2023
Cite: reference for this paper using: BibTeX, LaTeX, Text/Word, RIS, EndNote
TUPM053
The SARAF-linac project status
2313
SNRC and CEA collaborate to the upgrade of the SARAF accelerator to 5 mA CW 40 MeV deuteron and proton beams (Phase 2). CEA is in charge of the design, construction and commissioning of the linac downstream the existing RFQ (SARAF-LINAC Project). The MEBT is now installed at SNRC and has been commissionined with beam. Transverse and longitudinal emittances have been measured and beam transport has been compared with TraceWin simulations. The low-beta HWR and superconducting solenoids have all achieved their design performances on Saclay test-stand. First cryomodule has been assembled and tested at Saclay and is being installed at SNRC. This paper presents the results of the MEBT commissioning, the qualification of the HWR and the solenoids and the test results of the first cryomodule.
  • N. Pichoff, A. Chance, G. Ferrand, F. Gougnaud, T. Plaisant, D. Uriot
    Commissariat à l'Energie Atomique et aux Energies Alternatives
  • J. Dumas, F. Senee, D. Simon
    Commissariat à l'Energie Atomique
  • H. Isakov, J. Luner, I. Mardor, A. Perry, E. Reinfeld, J. Rodnizki, I. Shmuely, R. Weiss-Babai, L. Weissman
    Soreq Nuclear Research Center
Paper: TUPM053
DOI: reference for this paper: 10.18429/JACoW-IPAC2023-TUPM053
About:  Received: 09 May 2023 — Revised: 10 May 2023 — Accepted: 19 Jun 2023 — Issue date: 26 Sep 2023