MOPAB001 Power Deposition in Superconducting Dispersion Suppressor Magnets Downstream of the Betatron Cleaning Insertion for HL-LHC 37
 
  • A. Waets, C. Bahamonde Castro, E. Belli, R. Bruce, N. Fuster-Martínez, A. Lechner, A. Mereghetti, S. Redaelli, M. Sabaté-Gilarte, E. Skordis
    CERN, Meyrin, Switzerland
 
  Funding: Research supported by the HL-LHC project
The power deposited in dispersion suppressor magnets downstream of the Large Hadron Collider (LHC) betatron cleaning insertion is governed by off-momentum particles scattered out of the primary collimators. In order to mitigate the risk of magnet quenches during periods of short beam lifetime in future High-Luminosity (HL-LHC) operation, new dispersion suppressor (DS) collimators are considered for installation (one per beam). In this paper, we present FLUKA simulations for both protons and Pb ions at 7 TeV, predicting the power deposition in the DS magnets, including the new higher-field dipoles 11T which are needed to integrate the collimator in the cold region next to the cleaning insertion. The simulated power deposition levels for the adopted HL-LHC collimator configuration and settings are used to assess the quench margin by comparison with the present estimated quench levels.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2021-MOPAB001  
About • paper received ※ 19 May 2021       paper accepted ※ 07 July 2021       issue date ※ 16 August 2021  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPAB002 Risk of Halo-Induced Magnet Quenches in the HL-LHC Beam Dump Insertion 41
 
  • J.B. Potoine, A. Apollonio, E. Belli, C. Bracco, R. Bruce, M. D’Andrea, R. García Alía, A. Lechner, G. Lerner, S. Morales Vigo, S. Redaelli, V. Rizzoglio, E. Skordis, A. Waets
    CERN, Meyrin, Switzerland
  • F. Wrobel
    IES, Montpellier, France
 
  Funding: Research supported by the HL-LHC project
After the High Luminosity (HL-LHC) upgrade, the LHC will be exposed to a higher risk of magnet quenches during periods of short beam lifetime. Collimators in the extraction region (IR6) assure the protection of magnets against asynchronous beam dumps, but they also intercept a fraction of the beam halo leaking from the betatron cleaning insertion. In this paper, we assess the risk of quenching nearby quadrupoles during beam lifetime drops. In particular, we present an empirical analysis of halo losses in IR6 using LHC Run 2 (2015-2018) beam loss monitor measurements. Based on these results, the halo-induced power density in magnet coils expected in HL-LHC is estimated using FLUKA Monte Carlo shower simulations.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2021-MOPAB002  
About • paper received ※ 19 May 2021       paper accepted ※ 13 July 2021       issue date ※ 22 August 2021  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)