Paper |
Title |
Page |
WEPMP040 |
Machine Protection Aspects of High-Voltage Flashovers of the LHC Beam Dump Dilution Kickers |
2418 |
|
- C. Wiesner, W. Bartmann, C. Bracco, M. Calviani, E. Carlier, L. Ducimetière, M.I. Frankl, M.A. Fraser, S.S. Gilardoni, B. Goddard, V. Gomes Namora, T. Kramer, A. Lechner, N. Magnin, M. Meddahi, A. Perillo-Marcone, T. Polzin, L.C. Richtmann, V. Rizzoglio, V. Senaj, J.A.F. Somoza, D. Wollmann
CERN, Meyrin, Switzerland
|
|
|
The LHC Beam Dump System is required to safely dispose of the energy of the stored beam. In order to reduce the energy density deposited in the beam dump, a dedicated dilution system is installed. On July 14, 2018, during a regular beam dump at 6.5 TeV beam energy, a high-voltage flashover of two vertical dilution kickers was observed, leading to a voltage breakdown and reduced dilution in the vertical plane. It was the first incident of this type since the start of LHC beam operation. In this paper, the flashover event is described and the implications analysed. Circuit simulations of the current in the magnet coil as well as simulations of the resulting beam sweep pattern are presented and compared with the measurements. The criticality of the event is assessed and implications for future failure scenarios are discussed.
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-IPAC2019-WEPMP040
|
|
About • |
paper received ※ 14 May 2019 paper accepted ※ 20 May 2019 issue date ※ 21 June 2019 |
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
THPRB079 |
DC Testing and Phase Resolved Partial Discharge Measurements of the New Trigger Transformers for the LHC Beam Dump Kickers |
3998 |
|
- T. Stadlbauer, A. Chmielinska, L. Ducimetière, D. Kontelis, T. Kramer, V. Senaj
CERN, Geneva, Switzerland
|
|
|
During LS2 the LHC beam dump kicker pulse generators will be subject to a substantial consolidation program. One major part is the replacement of the existing GTO stack trigger transformer by a new more performant one. The transformer is assembled, moulded and tested in-house. Part of the validation procedure are standard DC tests and subsequent discharge monitoring as well as newly introduced phase resolved partial discharge measurements. This paper briefly highlights the trigger transformer parameters and construction and outlines in detail the testing and partial discharge measurements. It concludes with a comparison and analysis of the results of the different measurement techniques.
|
|
DOI • |
reference for this paper
※ https://doi.org/10.18429/JACoW-IPAC2019-THPRB079
|
|
About • |
paper received ※ 14 May 2019 paper accepted ※ 23 May 2019 issue date ※ 21 June 2019 |
|
Export • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|