Author: Plostinar, D.C.
Paper Title Page
MOPRB045 Future High Power Proton Drivers for Neutrino Beams 662
 
  • D.C. Plostinar, M. Eshraqi, B. Gålnander
    ESS, Lund, Sweden
  • V.A. Lebedev
    Fermilab, Batavia, Illinois, USA
  • C.R. Prior
    STFC/RAL/ISIS, Chilton, Didcot, Oxon, United Kingdom
  • Y. Sato
    KEK, Ibaraki, Japan
  • J.Y. Tang
    IHEP, Beijing, People’s Republic of China
 
  Funding: ESSnuSB has received funding from the European Union’s Horizon 2020 research and innovation programme under grant agreement No 7774.
Over the last two decades, significant efforts were made through several international studies to identify and develop technical solutions for potential Neutrino Factories and Superbeam Facilities. With many questions now settled, as well as clearer R&D needs, various proposals are being made for future facilities in China, Europe, Japan and North America. These include both developing and adapting existing machines as well as green-field solutions. In this paper, we review all the major accelerator programmes aimed at delivering high-power proton beams for neutrino physics.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-MOPRB045  
About • paper received ※ 22 May 2019       paper accepted ※ 23 May 2019       issue date ※ 21 June 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPTS103 First Results of Beam Commissioning on the ESS Site for the Ion Source and Low Energy Beam Transport 1118
 
  • R. Miyamoto, R.E. Bebb, E.C. Bergman, B. Bertrand, H. Danared, C.S. Derrez, E.M. Donegani, M. Eshraqi, J.F. Esteban Müller, T. Fay, V. Grishin, B. Gålnander, S. Haghtalab, H. Hassanzadegan, A. Jansson, H. Kocevar, E. Laface, Y. Levinsen, M. Mansouri, C.A. Martins, J.P.S. Martins, N. Milas, M. Muñoz, E. Nilsson, D.C. Plostinar, C. Rosati, T.J. Shea, A.G. Sosa, R. Tarkeshian, L. Tchelidze, C.A. Thomas, P.L. van Velze
    ESS, Lund, Sweden
  • I. Bergstrom
    CERN, Meyrin, Switzerland
  • L. Celona, L. Neri
    INFN/LNS, Catania, Italy
 
  The European Spallation Source (ESS), currently under construction in Lund, Sweden, will be a spallation neutron source driven by a proton linac of an unprecedented 5 MW beam power. Such a high power requires its ion source (IS) to produce proton beam pulses at 14 Hz with a high peak current more than 62.5 mA and a long plateau up to §I{3}{ms}. The IS and the following low energy beam transport (LEBT) section were manufactured and tested with beam to meet ESS requirements at INFN-LNS and delivered to ESS towards the end of 2017. Beam commissioning of these two sections on the ESS site has started in September 2018 and will continue until the end of June 2019. This paper provides an overview on this first beam commissioning period at ESS and also presents results of IS characterization and testing on LEBT functionalities.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-MOPTS103  
About • paper received ※ 20 May 2019       paper accepted ※ 23 May 2019       issue date ※ 21 June 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)