Author: Plaisant, Th.
Paper Title Page
MOPTS007 SARAF Equipped Cavity Test Stand (ECTS) at CEA 852
 
  • O. Piquet, C. Boulch, D. Chirpaz-Cerbat, G. Ferrand, F. Gohier, T.J. Joannem, G. Monnereau, Th. Plaisant
    CEA-IRFU, Gif-sur-Yvette, France
  • D. Braud, P. Carbonnier, P. Guiho, L. Maurice, J. Plouin, P. Sahuquet, N. Solenne
    CEA-DRF-IRFU, France
  • F. Gouit, A. Pérolat
    CEA, Gif-sur-Yvette, France
 
  CEA is committed to delivering a Medium Energy Beam Transfer line and a Super Conducting Linac (SCL) for SARAF accelerator in order to accelerate 5mA beam of either protons from 1.3MeV to 35MeV or deuterons from 2.6 MeV to 40.1MeV. The SCL consists in 4 cryomodules separated by warm section housing beam diagnostics. The two first identical cryomodules hosts respectively 6 and 7 half-wave resonator (HWR) low beta (0.091) cavities 176MHz. In order to test the cavity with its tuner and coupler and validate some design consideration, the Equipped Cavity Test Stand (ECTS) has been designed and will be presented.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-MOPTS007  
About • paper received ※ 07 May 2019       paper accepted ※ 20 May 2019       issue date ※ 21 June 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPTS116 The SARAF-LINAC Project 2019 Status 4352
 
  • N. Pichoff, R.D. Duperrier, G. Ferrand, B. Gastineau, F. Gougnaud, M. Jacquemet, C. Madec, O. Piquet, Th. Plaisant, F. Senée, D. Uriot
    CEA-IRFU, Gif-sur-Yvette, France
  • D. Berkovits, J. Luner, A. Perry, E. Reinfeld
    Soreq NRC, Yavne, Israel
 
  SNRC and CEA collaborate to the upgrade of the SARAF accelerator to 5 mA CW 40 MeV deuteron and proton beams (Phase 2). CEA is in charge of the design, construction and commissioning of the MEBT line and the superconducting linac (SARAF-LINAC Project). The prototypes of the 176 MHz NC rebuncher, SC cavities, RF coupler and SC solenoid-Package have been tested recently. Meanwhile, the cryomodules technical specifications have been written and called for tender. This paper presents the status of the SARAF-LINAC Project at April 2019.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-THPTS116  
About • paper received ※ 13 May 2019       paper accepted ※ 22 May 2019       issue date ※ 21 June 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)