Paper | Title | Page |
---|---|---|
TUPTS006 | Tests at High RF Power of the ESS Medium Beta Cryomodule Demonstrator | 1940 |
|
||
CEA is in charge of the 30 elliptical medium and high-beta cryomodules to be installed in the ESS tunnel in Lund, Sweden. Before launching the assembly of the series cryomodules, CEA developed a medium-beta cryomodule technology demonstrator in a collaboration with IPNO, LASA and ESS. This paper briefly presents the cryomodule assembly and summarizes the main results of the high RF power tests performed in 2018 in a dedicated test stand in CEA Saclay. The main ESS requirements were reached: Eacc = 16.7 MV/m in cavities, Pforward = 1.1 MW in power couplers, RF pulses length = 3.6 ms at 14 Hz. The piezo tuners efficiently compensated the Lorentz forces detuning and could stabilize the accelerating field better than 1% over the full length of the expected ESS 2.86 ms beam pulse without any LLRF regulation system. Following this successful validation CEA started the assembly of the first ESS medium-beta series cryomodule | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-TUPTS006 | |
About • | paper received ※ 06 May 2019 paper accepted ※ 22 May 2019 issue date ※ 21 June 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
WEPRB007 | RF Commissioning of the SPIRAL2 RFQ in CW Mode and Beyond Nominal Field | 2804 |
|
||
The SPIRAL2 RFQ was recently successfully commissioned at nominal voltage of 114 kV, corresponding to 1.65 Kilpatrick factor. The paper describes limitations of the RFQ main subsystems, cavity conditioning difficulties, as well as changes implemented in the LLRF and automatic procedures to simplify turn on and operation of the whole system. | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-WEPRB007 | |
About • | paper received ※ 26 April 2019 paper accepted ※ 22 May 2019 issue date ※ 21 June 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
MOPTS007 | SARAF Equipped Cavity Test Stand (ECTS) at CEA | 852 |
|
||
CEA is committed to delivering a Medium Energy Beam Transfer line and a Super Conducting Linac (SCL) for SARAF accelerator in order to accelerate 5mA beam of either protons from 1.3MeV to 35MeV or deuterons from 2.6 MeV to 40.1MeV. The SCL consists in 4 cryomodules separated by warm section housing beam diagnostics. The two first identical cryomodules hosts respectively 6 and 7 half-wave resonator (HWR) low beta (0.091) cavities 176MHz. In order to test the cavity with its tuner and coupler and validate some design consideration, the Equipped Cavity Test Stand (ECTS) has been designed and will be presented. | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-MOPTS007 | |
About • | paper received ※ 07 May 2019 paper accepted ※ 20 May 2019 issue date ※ 21 June 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
MOPTS008 | ESS RFQ: Construction Status and Power Couplers Qualification | 855 |
|
||
The 352 MHz Radio Frequency Quadrupole (RFQ) for the European Spallation Source ERIC (ESS) will be de-livered during 2019. It is provided by CEA, IRFU, Sac-lay/France. It consists of five sections with a total length of 4.6 m and accelerates the proton beam from 75 keV up to 3.6 MeV. It will be feed with 1.6 MW peak power through two coaxial loop couplers. This paper will present the manufacturing status of the five sections and the qualification test of the RF power couplers. | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-MOPTS008 | |
About • | paper received ※ 07 May 2019 paper accepted ※ 21 May 2019 issue date ※ 21 June 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
WEPRB010 | RF Power Test of the Rebuncher for Saraf-Linac | 2815 |
|
||
Funding: SNRC Three normal conducting rebunchers will be installed at the Medium Energy Beam Transport (MEBT) of the SARAF-LINAC phase II [saraf]. The MEBT line is designed to follow a 1.3 MeV/u RFQ, is about 5 m long, and contains three 176 MHz rebunchers providing a field integral of 105 kV. CEA is in charge of the design and fabrication of the Cu plated stainless steel, 3-gap rebuncher. The high power tests and RF conditioning have been successfully performed at the CEA Saclay on the first cavity. A solid state power amplifier, which has been developed by SNRC and has been used for the RF tests. The cavity has shown a good performance according to calculations, regarding the dissipated power, peak temperatures and coupling factor. RF conditioning was started with a duty cycle of 1\% and increased gradually until continuous wave (CW), which is the nominal working mode in SARAF-LINAC. |
||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-WEPRB010 | |
About • | paper received ※ 09 May 2019 paper accepted ※ 22 May 2019 issue date ※ 21 June 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
WEPTS118 | Results of CEA Tests of SARAF Couplers Prototypes | 3382 |
|
||
CEA is committed to delivering a Medium Energy Beam Transfer line and a superconducting linac (SCL) for SARAF accelerator in order to accelerate 5 mA beam of either protons from 1.3 MeV to 35 MeV or deuterons from 2.6 MeV to 40 MeV. The SCL consists in 4 cryomodules. The first two cryomodules host 6 and 7 half-wave resonator (HWR) low beta cavities (β = 0.09) at 176 MHz. The last two identical cryomodule will host 7 HWR high-beta cavities (β = 0.18) at 176 MHz. The maximal required power to be transmitted to the beam is 11.4 kW for high-beta cavity couplers. This document presents the results of the coupler tests and conditioning. | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-WEPTS118 | |
About • | paper received ※ 23 April 2019 paper accepted ※ 22 May 2019 issue date ※ 21 June 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
THPTS116 | The SARAF-LINAC Project 2019 Status | 4352 |
|
||
SNRC and CEA collaborate to the upgrade of the SARAF accelerator to 5 mA CW 40 MeV deuteron and proton beams (Phase 2). CEA is in charge of the design, construction and commissioning of the MEBT line and the superconducting linac (SARAF-LINAC Project). The prototypes of the 176 MHz NC rebuncher, SC cavities, RF coupler and SC solenoid-Package have been tested recently. Meanwhile, the cryomodules technical specifications have been written and called for tender. This paper presents the status of the SARAF-LINAC Project at April 2019. | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-THPTS116 | |
About • | paper received ※ 13 May 2019 paper accepted ※ 22 May 2019 issue date ※ 21 June 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
THPTS117 | Results of CEA Tests of SARAF Cavities Prototypes | 4356 |
|
||
CEA is committed to delivering a Medium Energy Beam Transfer line and a superconducting linac (SCL) for SARAF accelerator in order to accelerate 5mA beam of either protons to 35 MeV or deuterons to 40 MeV. The SCL consists in 4 cryomodules. The first two cryomodules host 6 & 7 half-wave resonator (HWR) low beta cavities (β = 0.09) at 176 MHz, and the last two crymodules host 7 HWR medium beta cavities (β = 0.18). The low beta prototype was qualified, the medium beta is being qualified. The results of the RF tests will be presented in this poster. | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-THPTS117 | |
About • | paper received ※ 23 April 2019 paper accepted ※ 23 May 2019 issue date ※ 21 June 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |