Paper | Title | Page |
---|---|---|
WEPMP040 | Machine Protection Aspects of High-Voltage Flashovers of the LHC Beam Dump Dilution Kickers | 2418 |
|
||
The LHC Beam Dump System is required to safely dispose of the energy of the stored beam. In order to reduce the energy density deposited in the beam dump, a dedicated dilution system is installed. On July 14, 2018, during a regular beam dump at 6.5 TeV beam energy, a high-voltage flashover of two vertical dilution kickers was observed, leading to a voltage breakdown and reduced dilution in the vertical plane. It was the first incident of this type since the start of LHC beam operation. In this paper, the flashover event is described and the implications analysed. Circuit simulations of the current in the magnet coil as well as simulations of the resulting beam sweep pattern are presented and compared with the measurements. The criticality of the event is assessed and implications for future failure scenarios are discussed. | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-WEPMP040 | |
About • | paper received ※ 14 May 2019 paper accepted ※ 20 May 2019 issue date ※ 21 June 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
THPRB072 | Operational Experience of a Prototype LHC Injection Kicker Magnet with a Low SEY Coating and Redistributed Power Deposition | 3974 |
|
||
Funding: This research was supported by the HL-LHC project In the event that it is necessary to exchange an LHC injection kicker magnet (MKI), the newly installed kicker magnet would limit HL-LHC operation for a few hundred hours due to dynamic vacuum activity. A surface coating with a low secondary electron yield, applied to the inner surface of an alumina tube to reduce dynamic vacuum activity without increasing the probability of UFOs, and which is compatible with the high voltage environment, was included in a prototype MKI installed in the LHC during the 2017-18 Year End Technical Stop. In addition, this MKI included an upgrade to relocate a significant portion of beam induced power from the yoke to a ’damping element’: this element is not at pulsed high voltage. The effectiveness of the upgrades has been demonstrated during LHC operation, hence a future version will include water cooling of this ’damping element’. This paper reviews dynamic vacuum around the MKIs and summarizes operational experience of the upgraded MKI. |
||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-THPRB072 | |
About • | paper received ※ 08 April 2019 paper accepted ※ 23 May 2019 issue date ※ 21 June 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
THPRB078 | Performance Validation of the Existing and Upgraded PS Injection Kicker | 3994 |
|
||
The CERN PS injection kicker KFA45 will be upgraded in the framework of the LHC Injector Upgrade (LIU) project to allow for injection of 2 GeV proton beams. This paper summarizes the recent efforts to validate beam based waveform measurements, Pspice simulations and current waveform measurements by direct magnetic field measurements in the aperture of the existing system. The magnetic probe, associated measurement hardware design and measurements results are discussed. The paper concludes with a performance comparison and an outlook to future waveform tuning possibilities. | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-THPRB078 | |
About • | paper received ※ 14 May 2019 paper accepted ※ 22 May 2019 issue date ※ 21 June 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
THPRB079 | DC Testing and Phase Resolved Partial Discharge Measurements of the New Trigger Transformers for the LHC Beam Dump Kickers | 3998 |
|
||
During LS2 the LHC beam dump kicker pulse generators will be subject to a substantial consolidation program. One major part is the replacement of the existing GTO stack trigger transformer by a new more performant one. The transformer is assembled, moulded and tested in-house. Part of the validation procedure are standard DC tests and subsequent discharge monitoring as well as newly introduced phase resolved partial discharge measurements. This paper briefly highlights the trigger transformer parameters and construction and outlines in detail the testing and partial discharge measurements. It concludes with a comparison and analysis of the results of the different measurement techniques. | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-THPRB079 | |
About • | paper received ※ 14 May 2019 paper accepted ※ 23 May 2019 issue date ※ 21 June 2019 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |