Author: Jorat, L.O.
Paper Title Page
WEPMP022 Design and Construction of the CERN SPS Extraction Protection Elements for LIU 2359
 
  • B. Balhan, C. Baud, J.C.C.M. Borburgh, M.A. Fraser, M. Hourican, L.O. Jorat, F.-X. Nuiry, S. Pianese
    CERN, Geneva, Switzerland
 
  At CERN, the SPS synchrotron is equipped with two fast extraction channels towards the LHC. As a part of the LHC injector upgrade project (LIU), the protection devices upstream of the septa in both extraction channels will be upgraded. Various failure scenarios have been studied and presented in the past, but the definitive approach for the equipment protection upgrade for each channel has now been determined. This paper describes the consequences of the most significant failure scenarios and the impact of the heat deposition in the diluter. The resulting material stresses are evaluated. The detailed layout for the extraction protection equipment for each extraction channel is outlined. The final layout consists of a extended diluter in Long Straight Section (LSS) 6 (TPSG6) and the installation of an additional movable absorber (TPSC4) upstream of the quadrupole in front of the existing protection equipment in LSS 4. The detailed mechanical design of the TPSC4 and the construction status of both TPSC4 and TPSG6 are discussed.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-WEPMP022  
About • paper received ※ 10 May 2019       paper accepted ※ 20 May 2019       issue date ※ 21 June 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPMP039 The New Injection Region of the CERN PS Booster 2414
 
  • W.J.M. Weterings, C. Bracco, L.O. Jorat, M. Meddahi, R. Noulibos, P. Van Trappen
    CERN, Geneva, Switzerland
 
  During the Long Shutdown 2 (LS2) at CERN, the new Linac4 (L4) accelerator will be connected to the PS Booster (PSB) to inject 160 MeV H beam into the 4 superposed PSB rings. In order to achieve this, we have designed, built and pre-assembled a completely new H charge-exchange injection chicane system, with a carbon stripping foil unit to convert the negative hydrogen ions into protons by stripping off the electrons. In parallel, we have built and installed a test stand in the L4 transfer line enabling us to gain valuable experience with operation of the stripping foil system and to evaluate different foil types during the L4 reliability runs. This paper describes the final design of the new PSB injection region and reports on the important test results obtained with the stripping foil test stand.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-WEPMP039  
About • paper received ※ 10 May 2019       paper accepted ※ 20 May 2019       issue date ※ 21 June 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)