Author: Franberg, H.
Paper Title Page
MOPTS006 Final Results of the SPIRAL2 Injector Commissioning 848
 
  • R. Ferdinand, M. Di Giacomo, H. Franberg, J.-M. Lagniel, G. Normand, A. Savalle
    GANIL, Caen, France
  • D. Uriot
    CEA-DRF-IRFU, France
 
  The SPIRAL2 injector, made up of a 5 mA p-d ion source, a 1 mA heavy ion source (up to A/Q = 3) and a CW 0.75 MeV/u RFQ, has been commissioned in parallel with the superconducting linac installation. This com-missioning is successfully completed now and the Diag-nostic plate (D-plate) used to characterize the injector beams is removed. This paper presents the results ob-tained with the reference particles (H+, 4He2+, 18O6+ and 40Ar14+) and a comparison with the simulations. The connexion to the SC linac and the future linac beam commissioning is briefly described.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-MOPTS006  
About • paper received ※ 12 May 2019       paper accepted ※ 20 May 2019       issue date ※ 21 June 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPRB007 RF Commissioning of the SPIRAL2 RFQ in CW Mode and Beyond Nominal Field 2804
 
  • M. Di Giacomo, R. Ferdinand, H. Franberg, J.-M. Lagniel, G. Normand
    GANIL, Caen, France
  • M. Desmons, P. Galdemard, Y. Lussignol, O. Piquet, S. Sube
    CEA-DRF-IRFU, France
 
  The SPIRAL2 RFQ was recently successfully commissioned at nominal voltage of 114 kV, corresponding to 1.65 Kilpatrick factor. The paper describes limitations of the RFQ main subsystems, cavity conditioning difficulties, as well as changes implemented in the LLRF and automatic procedures to simplify turn on and operation of the whole system.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2019-WEPRB007  
About • paper received ※ 26 April 2019       paper accepted ※ 22 May 2019       issue date ※ 21 June 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)