TUPAB045 Design and Construction of a Pre-Buncher for Iranian Low Energy Linear Accelerator 1428
 
  • S. Ahmadiannamin
    ILSF, Tehran, Iran
  • M. Bahrami, M.R. Khalvati, M. Lamehi, H. Shaker, M. Shirshekan
    IPM, Tehran, Iran
 
  Iranian IPM low energy linear accelerator project (e-Linac) is in its final steps for commissioning. Beam dynamic simulations with and without Pre-buncher prior to buncher was done. The results represent improvement in capturing efficiency better than 25% by application of Pre-buncher cavity. In this paper, we present the simulation, construction, RF measurements and vacuum test results. After construction, we measured RF reflection coefficient better than -33 dB in the nominal frequency of 2997.9 MHz with quality factor of 4500.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-TUPAB045  