Author: Huang, M.Y.
Paper Title Page
MOPIK036 Study of the Magnetizing Relationship of the Kickers for CSNS 582
 
  • M.Y. Huang, Y.W. An, S. Fu, N. Huang, W. Kang, Y.Q. Liu, L. Shen, L. Wang, S. Wang, Y.W. Wu, S.Y. Xu, J. Zhai, J. Zhang
    IHEP, Beijing, People's Republic of China
 
  Funding: Work supported by National Natural Science Foundation of China (11205185)
The extraction system of CSNS mainly consists of two kinds of magnets: eight kickers and one lambertson magnet. In this paper, firstly, the magnetic test results of the eight kickers were introduced and then the filed uniformity and magnetizing relationship of the kickers were given. Secondly, during the beam commissioning in the future, in order to obtain more accurate magnetizing relationship, a new method to measure the magnetizing coefficients of the kickers by the real extraction beam was given and the data analysis would also be processed.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-MOPIK036  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUOBA1 Beam Commissioning Results of the CSNS Linac 1223
 
  • J. Peng, Y.W. An, S. Fu, L. Huang, M.Y. Huang, Y. Li, Z.P. Li, S. Wang, S.Y. Xu, Y. Yuan
    IHEP, Beijing, People's Republic of China
  • M.T. Li, Y.D. Liu
    CSNS, Guangdong Province, People's Republic of China
 
  The China Spallation Neutron Source(CSNS) accelera-tor systems is designed to deliver a 1.6GeV, 100kW pro-ton beam to a solid metal target for neutron scattering research. It consists of a 50keV H Ion Source, a 3MeV Radio Frequency Quadrupole (RFQ), an 80MeV Drift Tube Linac (DTL), and a 1.6GeV Rapid-cycling Synchro-tron (RCS). The beam commissioning has been started since April 2015. The Front End and three of the four DTL tanks have been commissioned, while the last tank and the RCS will be commissioned at the autumn this year. At the end of the DTL3, beam has been accelerated to 61MeV with nearly 100% transmission, other parame-ters such as peak current, transverse emittance and beam orbit have reached the design goal. Results and status of the beam commissioning program will be presented.
*This work is supported by National Natural Science Foundation of China (11505101).
**E-mail:pengjun@ihep.ac.cn
 
slides icon Slides TUOBA1 [4.272 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-TUOBA1  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)