MOPVA005 Status of the Berlin Energy Recovery Linac Project BERLinPro 855
 
  • M. Abo-Bakr, W. Anders, K.B. Bürkmann-Gehrlein, A.B. Büchel, P. Echevarria, A. Frahm, H.-W. Glock, F. Glöckner, F. Göbel, B.D.S. Hall, S. Heling, H.-G. Hoberg, A. Jankowiak, C. Kalus, T. Kamps, G. Klemz, J. Knedel, J. Knobloch, J. Kolbe, G. Kourkafas, J. Kühn, B.C. Kuske, J. Kuszynski, D. Malyutin, A.N. Matveenko, M. McAteer, A. Meseck, C.J. Metzger-Kraus, R. Müller, A. Neumann, N. Ohm, K. Ott, E. Panofski, F. Pflocksch, J. Rahn, M. Schmeißer, O. Schüler, M. Schuster, J. Ullrich, A. Ushakov, J. Völker
    HZB, Berlin, Germany
 
  Funding: Work supported by German Bundesministerium für Bildung und Forschung, Land Berlin, and grants of Helmholtz Association.
The Helmholtz-Zentrum Berlin is constructing the Energy Recovery Linac Prototype BERLinPro, a demonstration facility for the science and technology of ERLs for future light source applications. BERLinPro is designed to accelerate a high current (100 mA, 50 MeV), high brilliance (norm. emittance below 1 mm mrad) cw electron beam. We report on the project status. This includes the completion of the building and the installation of the first accelerator components as well as the assembly of the SRF gun and GunLab beam diagnostics, which are now ready for commissioning.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-MOPVA005  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPVA010 Setup and Status of an SRF Photoinjector for Energy-Recovery Linac Applications 865
 
  • T. Kamps, D. Böhlick, A.B. Büchel, M. Bürger, P. Echevarria, A. Frahm, F. Göbel, S. Heling, A. Jankowiak, S. Keckert, H. Kirschner, G. Klemz, J. Knobloch, G. Kourkafas, J. Kühn, O. Kugeler, A.N. Matveenko, A. Neumann, N. Ohm-Krafft, E. Panofski, F. Pfloksch, S. Rotterdam, M.A.H. Schmeißer, M. Schuster, H. Stein, J. Ullrich, A. Ushakov, J. Völker
    HZB, Berlin, Germany
  • I. Will
    MBI, Berlin, Germany
 
  Funding: The work is funded by the Helmholtz-Association, BMBF, the state of Berlin and HZB.
The Superconducting RF (SRF) photoinjector programme for the energy-recovery linac (ERL) test facility BERLinPro sets out to push the brightness and average current limits for ERL electron sources by tackling the main challenges related to beam dynamics of SRF photoinjectors, the incorporation of high quantum efficiency (QE) photocathodes, and suppression of unwanted beam generation. The paper details the experimental layout of the SRF photoinjector and the gun test facility GunLab at Helmholtz-Zentrum Berlin.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-MOPVA010  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPVA049 First Commissioning of an SRF Photo-Injector Module for BERLinPro 971
 
  • A. Neumann, A. Burrill, D. Böhlick, A.B. Büchel, M. Bürger, P. Echevarria, A. Frahm, H.-W. Glock, F. Göbel, S. Heling, K. Janke, T. Kamps, S. Keckert, S. Klauke, G. Klemz, J. Knobloch, G. Kourkafas, J. Kühn, O. Kugeler, N. Ohm, E. Panofski, H. Plötz, S. Rotterdam, M. Schenk, M.A.H. Schmeißer, M. Schuster, H. Stein, Y. Tamashevich, J. Ullrich, A. Ushakov, J. Völker
    HZB, Berlin, Germany
  • A. Matheisen, M. Schmökel
    DESY, Hamburg, Germany
 
  Funding: Work supported by German Bundesministerium für Bildung und Forschung, Land Berlin, and grants of Helmholtz Association.
Helmholtz-Zentrum Berlin (HZB) is currently building an high average current superconducting ERL to demonstrate ERL operation with low normalized beam emittance of 1 mm·mrad at 100mA and short pulses of about 2 ps. For the injector section a series of SRF photoinjector cavities is being developed. The medium power prototype presented here features a 1.4 x λ/2 cell SRF cavity with a normal-conducting, high quantum efficiency CsK2Sb cathode, implementing a modified HZDR-style cathode insert. This injector potentially allows for 6 mA beam current at up to 3.5 MeV kinetic energy. In this contribution, the first RF commissioning results of the photo-injector module will be presented and compared to the level of performance during the cavity production and string assembly process.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-MOPVA049  