MOPVA096 The Crab Cavities Cryomodule for SPS Test 1081
 
  • C. Zanoni, A. Amorim Carvalho, K. Artoos, S. Atieh, K. Brodzinski, R. Calaga, O. Capatina, T. Capelli, F. Carra, L. Dassa, T. Dijoud, K. Eiler, G. Favre, P. Freijedo Menendez, M. Garlaschè, L. Giordanino, S.A.E. Langeslag, R. Leuxe, H. Mainaud Durand, P. Minginette, M. Narduzzi, V. Rude, M. Sosin, J.S. Swieszek
    CERN, Geneva, Switzerland
  • T.J. Jones, N. Templeton
    STFC/DL, Daresbury, Warrington, Cheshire, United Kingdom
 
  RF Crab Cavities are an essential part of the HL-LHC upgrade. Two concepts of such systems are being developed: the Double Quarter Wave (DQW) and the RF Dipole (RFD). A cryomodule with two DQW cavities is in advanced fabrication stage at CERN for their tests with protons in the SPS during the 2018 run. The cavities must be operated at 2 K, without excessive heat loads, in a low magnetic environment and in compliance with CERN safety guidelines on pressure and vacuum systems. A large set of components, such as a thermal shield, a two layers magnetic shield, RF lines, helium tank and tuner is required for the successful and safe operation of the cavities. The assembly of all these components with the cavities and their couplers forms the cryomodule. An overview of the design and fabrication strategy of this cryomodule is presented. The main components are described along with the present status of cavity fabrication and processing and cryomodule assembly. The lesson learned from the prototypes, the helium tank above all, and first manufactured systems is also included.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-MOPVA096  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPIK085 HL-LHC Alignment Requirements and Associated Solutions 1893
 
  • H. Mainaud Durand, S. Bartolome-Jimenez, T. Dijoud, A. Herty, M. Sosin
    CERN, Geneva, Switzerland
  • M. Duquenne, V. Rude
    ESGT-CNAM, Le Mans, France
 
  To increase by more than 10 times the luminosity reach w.r.t the first 10 years of the LHC lifetime, the HL-LHC project will replace nearly 1.2 km of the accelerator during the Long Shutdown 3 scheduled in 2024 [1][2][3]. This paper presents the HL-LHC alignment and internal metrology requirements of all the new components to be installed, from the magnet components to the beam instrumentation and vacuum devices. As for the LHC, a combination of Hydrostatic Levelling Sensors (HLS) and Wire Positioning Sensors (WPS) is proposed for the alignment of the main components, but on a longer distance (210 m instead of 50 m), generating technical challenges for the installation of the stretched wire and for the maintenance of the alignment systems. Innovative measurements methods and instrumentation are under study to perform the position monitoring inside a cryostat of cold masses and crab cavities, in a cold (2K) and radioactive (1 MGy/year) environment, as well as to carry remote measurements in the tunnel of the intermediary components. The proposed solutions concerning the determination of the position and the re-adjustment of the components are detailed in this paper.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-TUPIK085  