TUPVA121 Shielding Calculations for the Commissioning Beam Dump During the First Stage Beam Commissioning of the ESS Warm Linac 2376
 
  • K. Batkov, L. Tchelidze
    ESS, Lund, Sweden
 
  Starting operations in 2019, the European Spallation Source will be a long pulsed neutron source powered by a 5 MW proton beam impinging on a rotating tungsten target. This study describes the results of shielding calculations performed to determine necessary shielding configuration during various steps of first stage beam commissioning of the ESS Linac. The first stage commissioning is divided in four steps with different beam energy, up to maximum 74 MeV. The commissioning beam dump shielding assessment is presented for each step of first stage commissioning and different beam parameters (energies, repetition rates, pulse lengths and currents).  