MOPAB033 Optics Development and Trajectory Tuning of BERLinPro at Low Energies 153
 
  • B.C. Kuske, M. Abo-Bakr
    HZB, Berlin, Germany
 
  Funding: Work supported by the German Bundesministerium fr Bildung und Forschung, Land Berlin and grants of the Helmholtz Association
The Berlin Energy Recovery Linac project has taken shape during the past year. The magnets have been set up in the newly constructed subterraneous hall; first electrons are expected in the SRF-gun test laboratory in June 2017. Starting in February 2018 the complete gun module will be transferred to the accelerator hall for the commissioning of BERLinPro. For the first months, operation is planned without further accelerating structures (booster and linac), due to delays in their fabrication. Several modes of operation are applicable at this early stage [1]. The available hardware is displayed and the adapted optics at 2.7 MeV and at 6.5 MeV (including the booster) are presented. The trajectory distortions under the influence of the earth magnetic field are studied. The concept for trajectory correction is outlined.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-MOPAB033  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPVA005 Status of the Berlin Energy Recovery Linac Project BERLinPro 855
 
  • M. Abo-Bakr, W. Anders, K.B. Bürkmann-Gehrlein, A.B. Büchel, P. Echevarria, A. Frahm, H.-W. Glock, F. Glöckner, F. Göbel, B.D.S. Hall, S. Heling, H.-G. Hoberg, A. Jankowiak, C. Kalus, T. Kamps, G. Klemz, J. Knedel, J. Knobloch, J. Kolbe, G. Kourkafas, J. Kühn, B.C. Kuske, J. Kuszynski, D. Malyutin, A.N. Matveenko, M. McAteer, A. Meseck, C.J. Metzger-Kraus, R. Müller, A. Neumann, N. Ohm, K. Ott, E. Panofski, F. Pflocksch, J. Rahn, M. Schmeißer, O. Schüler, M. Schuster, J. Ullrich, A. Ushakov, J. Völker
    HZB, Berlin, Germany
 
  Funding: Work supported by German Bundesministerium für Bildung und Forschung, Land Berlin, and grants of Helmholtz Association.
The Helmholtz-Zentrum Berlin is constructing the Energy Recovery Linac Prototype BERLinPro, a demonstration facility for the science and technology of ERLs for future light source applications. BERLinPro is designed to accelerate a high current (100 mA, 50 MeV), high brilliance (norm. emittance below 1 mm mrad) cw electron beam. We report on the project status. This includes the completion of the building and the installation of the first accelerator components as well as the assembly of the SRF gun and GunLab beam diagnostics, which are now ready for commissioning.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-MOPVA005  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPVA007 Simulations for Beam-Based Measurements in BERLinPro 859
 
  • M. McAteer, M. Abo-Bakr, J. Knedel, G. Kourkafas, B.C. Kuske, J. Völker
    HZB, Berlin, Germany
 
  BERLinPro is an energy recovery linac project whose goal is to establish the accelerator physics knowledge and technology needed to produce 50 MeV beams with high current, low normalized emittance, and low losses. Precise measurements of beam parameters are essential for demonstrating the achievement of performance goals. In this paper we present simulations for measurements of energy, energy spread, and bunch length using the tracking code Astra.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-MOPVA007  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
MOPVA008 Commissioning Considerations for BERLinPro 862
 
  • M. McAteer, M. Abo-Bakr, T. Kamps, G. Klemz, J. Kuszynski
    HZB, Berlin, Germany
  • I. Will
    MBI, Berlin, Germany
 
  BERLinPro is an energy recovery linac project whose goal is to establish the accelerator physics knowledge and technology needed to produce 50 MeV beams with high current, low normalized emittance, and low losses. The machine will be commissioned in phases beginning in 2018, and extensive planning is underway for start-up of the machine and to prepare for measurements to verify the achievement of target beam parameters. This paper outlines the planned phases for the commissioning of the machine, details the operational modes, and gives an overview of the diagnostics available for beam-based measurements to verify the achievement of performance goals.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-MOPVA008  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPIK012 The Magnets of BERLinPro: Specification, Design, Measurement and Quality Analysis 4124
 
  • A.N. Matveenko, M. Abo-Bakr, K.B. Bürkmann-Gehrlein
    HZB, Berlin, Germany
  • I.V. Davidyuk, O.A. Shevchenko, A.V. Utkin, N.A. Vinokurov
    BINP SB RAS, Novosibirsk, Russia
 
  Funding: Work supported by grants of Helmholtz Association VH-NG-636 and HRJRG-214
A total of 77 magnets form the magnetic lattice of the BERLinPro energy recovery linac prototype: 1+8+8 dipole magnets of three different types, 12+40 quadrupole magnets of two different types and 8 sextupole magnets have been produced by BINP. After the design phase, magnets production started in 2015, measurements and delivery took place in 2016, first assembly stage was finished in 03/2017. The motivation for the magnet specification and a summary of the basic design is given in this paper. Select-ed measurement data from the final acceptance tests are presented and analysed to ensure the magnet quality.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2017-THPIK012  