TUPOW034 Status Report of the Berlin Energy Recovery Linac Project BERLinPro 1827
 
  • M. Abo-Bakr, W. Anders, K.B. Bürkmann-Gehrlein, A.B. Büchel, P. Echevarria, A. Frahm, H.-W. Glock, F. Glöckner, F. Göbel, B.D.S. Hall, S. Heling, H.-G. Hoberg, A. Jankowiak, C. Kalus, T. Kamps, G. Klemz, J. Knobloch, J. Kolbe, G. Kourkafas, J. Kühn, B.C. Kuske, P. Kuske, J. Kuszynski, D. Malyutin, A.N. Matveenko, M. McAteer, A. Meseck, C.J. Metzger-Kraus, R. Müller, A. Neumann, N. Ohm, K. Ott, E. Panofski, F. Pflocksch, J. Rahn, J. Rudolph, M. Schmeißer, O. Schüler, M. Schuster, J. Ullrich, A. Ushakov, J. Völker
    HZB, Berlin, Germany
 
  Funding: Work supported by the German Bundesministerium für Bildung und Forschung, Land Berlin and grants of Helmholtz Association
The Helmholtz Zentrum Berlin is constructing the Energy Recovery Linac Prototype BERLinPro at the Berlin Adlershof site. The project is intended to expand the required accelerator physics and technology knowledge mandatory for the design, construction and operation of future synchrotron light sources. The project goal is the generation of a high current (100 mA), high brilliance (norm. emittance below 1 mm mrad) cw electron beam. We report on the project progress: since spring 2015 the building is under construction, ready for occupancy in January 2017. The planning phase for the first project stage is completed for the warm machine parts, the SRF gun and partly for the SRF booster. Most of the components have been ordered and are in fabrication with some already delivered. An update of the status of the various subprojects as well as a summary of future activities will be given. Project milestones and details of the timeline will be reviewed.
 
DOI • reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-TUPOW034  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPOW035 First LLRF Tests of BERLinPro Gun Cavity Prototype 1831
 
  • P. Echevarria, J. Knobloch, O. Kugeler, A. Neumann, A. Ushakov
    HZB, Berlin, Germany
  • K.P. Przygoda
    DESY, Hamburg, Germany
 
  The goal of Berlin Energy Recovery Linac Project (BERLinPro) is the generation of a 50 MeV, 100-mA low emittance (below 1 mm mrad) CW electron beam at 2 ps rms bunch duration or below. Three different types of 1.3 GHz SRF modules will be employed: the electron gun, the booster and the main linac. Precise RF amplitude and phase control are needed due to the beam recovery pro-cess. In this paper we describe the first tests of the Low Level RF control of the first injector prototype at the HoBiCaT facility, implemented in the digital VME-based LLRF controller developed by Cornell University. Tuner movement control by an mTCA.4 system, together with further plans of using this technology will be also presented.  