MOPOY009 ELENA: Installations and Preparations for Commissioning 860
 
  • C. Carli, W. Bartmann, P. Belochitskii, H. Breuker, F. Butin, T. Eriksson, R. Ostojić, S. Pasinelli, G. Tranquille
    CERN, Geneva, Switzerland
  • W. Oelert
    Johannes Gutenberg University Mainz, Institut für Physik, Mainz, Germany
 
  The Extra Low Energy Antiproton ring (ELENA) is a small 30 m circumference synchroton under construction at CERN to further decelerate antiprotons from the Antiproton Decelerator AD from 5.3 MeV to 100 keV. Controlled deceleration in a synchrotron equipped with an electron cooler to reduce emittances in all three planes will allow the existing AD experiments to increase substantially their antiproton capture efficiencies and render new experiments possible. Installation of the machine and lines needed for the commissioning of the ring are ongoing and commissioning is expected to start around mid-2016. The aim is to complete ELENA ring commissioning in November followed by the installation of new electrostatic transfer lines to existing experiments until autumn 2017. Status of ELENA installations and preparations for commissioning will be reported.  
DOI • reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-MOPOY009  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPMR027 CERN's Fixed Target Primary Ion Programme 1297
 
  • D. Manglunki, M.E. Angoletta, J. Axensalva, G. Bellodi, A. Blas, M.A. Bodendorfer, T. Bohl, S. Cettour-Cave, K. Cornelis, H. Damerau, I. Efthymiopoulos, A. Fabich, J.A. Ferreira Somoza, A. Findlay, P. Freyermuth, S.S. Gilardoni, S. Hancock, E.B. Holzer, S. Jensen, V. Kain, D. Küchler, A.M. Lombardi, A.I. Michet, M. O'Neil, S. Pasinelli, R. Scrivens, R. Steerenberg, G. Tranquille
    CERN, Geneva, Switzerland
 
  The renewed availability of heavy ions at CERN for the needs of the LHC programme has triggered the interest of the fixed-target community. The project, which involves sending several species of primary ions at various energies to the North Area of the Super Proton Synchrotron, has now entered its operational phase. The first argon run, with momenta ranging from 13 AGeV/c to 150 AGeV/c, took place from February 2015 to April 2015. This paper presents the status of the project, the performance achieved thus far and an outlook on future plans.  
DOI • reference for this paper ※ DOI:10.18429/JACoW-IPAC2016-TUPMR027  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)