Three accelerator facilities were built in the past few years, the 2.8 GeV electron positron collider BEPC, the heavy ion SSC cyclotron accelerator HIRFL and the 800 MeV synchrotron radiation storage ring HESYRL. Aimed at different research areas, they represent a new generation of accelerator in China. This report describes the design philosophy, the structure, performance as well as future improvements of the control systems of the these facilities.
|
|
DOI • |
reference for this paper
※ doi:10.18429/JACoW-ICALEPCS1991-S01SRA09
|
|
About • |
Received ※ 11 November 1991 — Accepted ※ 20 November 1991 — Issued ※ 04 December 1992 |
|
Cite • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|
S01SRA10 |
HESYRL Control System Status |
40 |
|
- C.-Y. Yao
USTC/NSRL, Hefei, Anhui, People’s Republic of China
|
|
|
HESYRL synchrotron radiation storage ring was completed in 1989 and has been in commissioning since then. Now it has met its design specification and is ready for synchrotron light experiments. Control system of the project was completed in 1989 and some modifications were made during commissioning. This paper describes its present configuration, status and upgrading plan.
|
|
DOI • |
reference for this paper
※ doi:10.18429/JACoW-ICALEPCS1991-S01SRA10
|
|
About • |
Received ※ 11 November 1991 — Accepted ※ 20 November 1991 — Issued ※ 04 December 1992 |
|
Cite • |
reference for this paper using
※ BibTeX,
※ LaTeX,
※ Text/Word,
※ RIS,
※ EndNote (xml)
|
|
|