Author: Medina, D.
Paper Title Page
TUPB01 The Installation and Commissioning of the AWAKE Stripline BPM 253
 
  • S. Liu, P.E. Dirksen, V.A. Verzilov
    TRIUMF, Vancouver, Canada
  • S.J. Gessner, F. Guillot-Vignot, D. Medina, L. Søby
    CERN, Geneva, Switzerland
 
  Funding: # TRIUMF contribution was supported by NSERC and CNRC
AWAKE (The Advanced Proton Driven Plasma Wakefield Acceleration Experiment at CERN) stripline BPMs are required to measure the position of the single electron bunch to a position resolution of less than 10 µm rms for electron charge of 100 pC to 1 nC. This paper describes the design, installation and commissioning of a such BPM system developed by TRIUMF (Canada). Total 12 BPMs and electronics had been installed on AWAKE beam lines and started commissioning since Fall of 2017. The calibration and measurement performance are also reviewed.
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IBIC2018-TUPB01  
About • paper received ※ 04 September 2018       paper accepted ※ 12 September 2018       issue date ※ 29 January 2019  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)