TUA1WD01 ESS Commissioning Plans 127
 
  • N. Milas, R. De Prisco, M. Eshraqi, Y. Levinsen, R. Miyamoto, M. Muñoz, D.C. Plostinar
    ESS, Lund, Sweden
 
  The ESS linac is currently under construction in Lund, Sweden, and once completed it will deliver an unprecedented 5 MW of average power. The ion source and LEBT commissioning starts in 2018 and will continue with the RFQ, MEBT and the first DTL tank next year and up to the end of the fourth DTL tank in 2020. This paper will summarize the commissioning plans for the normal conducting linac with focus on the ion source and LEBT and application development for both commissioning and operation.  
slides icon Slides TUA1WD01 [1.552 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-HB2018-TUA1WD01  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUA1WD02
KOMAC Operation and Future Plans  
 
  • Y.-S. Cho
    KAERI, Daejon, Republic of Korea
 
  This talk is about KOMAC operation and future plans.  
slides icon Slides TUA1WD02 [7.375 MB]  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUA1WD03 Commissioning Status and Plans of CSNS/RCS 133
 
  • S.Y. Xu, Y.W. An, J. Chen, M.Y. Huang, H.F. Ji, Y. Li, S. Wang
    IHEP, Beijing, People's Republic of China
  • X.H. Lu
    CSNS, Guangdong Province, People's Republic of China
 
  The China Spallation Neutron Source (CSNS) is an accelerator-based science facility. CSNS is designed to accelerate proton beam pulses to 1.6 GeV kinetic energy, striking a solid metal target to produce spallation neutrons. CSNS has two major accelerator systems, a linear accelerator (80 MeV Linac) and a 1.6 GeV rapid cycling synchrotron (RCS). The Beam commissioning of CSNS has been commissioned recently. Beam had been accelerated to 61 MeV at CSNS/Linac on April 24, 2017, and 1.6 GeV acceleration at CSNS/RCS was successfully accomplished on July 7, 2017 with the injection energy of 61 MeV. Beam had been accelerated to 80 MeV at CSNS/Linac on January 6, 2018, and 1.6 GeV acceleration at CSNS/RCS was successfully accomplished on January 18, 2018 with the injection energy of 80 MeV. The initial machine parameter tuning and various beam studies were completed. In this paper, the commissioning experiences are introduced.  
slides icon Slides TUA1WD03 [10.794 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-HB2018-TUA1WD03  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUA1WD04 High Intensity Proton Stacking at Fermilab: 700 kW Running 136
 
  • R. Ainsworth, P. Adamson, B.C. Brown, D. Capista, K.J. Hazelwood, I. Kourbanis, D.K. Morris, M. Xiao, M.-J. Yang
    Fermilab, Batavia, Illinois, USA
 
  As part of the Nova upgrades in 2012, the Recycler was repurposed as proton stacker for the Main Injector with the aim to deliver 700 kW. Since January 2017, this design power has been run routinely. The steps taken to commission the Recycler and run at 700 kW operationally will be discussed as well as plans for future running.  
slides icon Slides TUA1WD04 [62.832 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-HB2018-TUA1WD04  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)