WEZZO03 ECR3 Commissioning and Planning for C-14 Ion Beams at the Argonne Tandem Linac Accelerator System 157
 
  • R.H. Scott, R.C. Vondrasek
    ANL, Lemont, Illinois, USA
 
  Funding: U.S. Department of Energy, Office of Nuclear Physics, contract No. DE-AC02-06CH11357.
The Electron Cyclotron Resonance Ion Source ECR3* has recently been commissioned at the Argonne Tandem Linac Accelerator System (ATLAS) at Argonne National Laboratory. While ECR3 can provide many of the stable ATLAS beams, its other intended purpose is the production of C-14 ion beams which were previously produced by a now-retired negative ion source. This paper will discuss the final installation and commissioning of the ion source as well as the preparations for running C-14. A stable C-13 ethylene gas was used as a surrogate to determine the expected level of N-14 contamination when running C-14 since they are inseparable at ATLAS. We were also able to confirm consumption rates and charge state efficiencies under different C-13 running conditions in order to optimize the upcoming C-14 beam production.
*R. H. Scott, C. Dickerson, R. C. Pardo, and R. C. Vondrasek, "A New ECRIS Installation at the Argonne Tandem Linac Accelerator System", doi:10.18429/JACoW-ECRIS2016-WEPP14
 
slides icon Slides WEZZO03 [0.667 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-ECRIS2020-WEZZO03  
About • Received ※ 28 September 2020 — Revised ※ 30 September 2020 — Accepted ※ 03 December 2020 — Issue date ※ 19 April 2021
Cite • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)