MOPC103 Short Circuit Tests: First Step of LHC Hardware Commissioning Completion 304
 
  • B. Bellesia, E. Barbero-Soto, F. Bordry, M. P. Casas Lino, G.-J. Coelingh, G. Cumer, K. Dahlerup-Petersen, J.-C. Guillaume, J. Inigo-Golfin, V. Montabonnet, D. Nisbet, M. Pojer, R. Principe, F. Rodriguez-Mateos, R. I. Saban, R. Schmidt, H. Thiesen, A. Vergara-Fernández, M. Zerlauth
    CERN, Geneva
  • A. Castaneda, I. Romera Ramirez
    CIEMAT, Madrid
 
  The Large Hadron Collider operation relies on 1232 superconducting dipoles with a field of 8.33T and 400 superconducting quadrupoles with a strength of 220 T/m powered at 12kA, operating in superfluid He at 1.9K. For dipoles and quadrupoles as well as for many other magnets more than 1700 power converters are necessary to feed the superconducting circuits. Between October 2005 and September 2007 the so-called short circuit tests were carried-out in the 15 underground areas where the power converters of the superconducting circuits are located. The tests were aimed at the qualification of the normal conducting components of the circuits: the power converters, the normal conducting DC cables between the power converters and the LHC cryostat, the interlocks and energy extraction systems. In addition, the correct functioning of the infrastructure systems (AC distribution, water and air cooling, control system) were validated. The final validation test for each underground area was the powering of all converters at ultimate current during 24h. This approach highlighted a few problems that were solved long before the beginning of magnet commissioning and beam operation.  
WEPD028 Performance of the Superconducting Corrector Magnet Circuits during the Commissioning of the LHC 2470
 
  • W. Venturini Delsolaro, V. Baggiolini, A. Ballarino, B. Bellesia, F. Bordry, A. Cantone, M. P. Casas Lino, C. CastilloTrello, N. Catalan-Lasheras, Z. Charifoulline, C. Charrondiere, G. D'Angelo, K. Dahlerup-Petersen, G. De Rijk, R. Denz, M. Gruwe, V. Kain, M. Karppinen, B. Khomenko, G. Kirby, S. L.N. Le Naour, A. Macpherson, A. Marqueta Barbero, K. H. Mess, M. Modena, R. Mompo, V. Montabonnet, D. Nisbet, V. Parma, M. Pojer, L. Ponce, A. Raimondo, S. Redaelli, V. Remondino, H. Reymond, A. Rijllart, R. I. Saban, S. Sanfilippo, K. M. Schirm, R. Schmidt, A. P. Siemko, M. Solfaroli Camillocci, H. Thiesen, Y. Thurel, A. Vergara-Fernández, A. P. Verweij, R. Wolf, M. Zerlauth
    CERN, Geneva
  • A. Castaneda, I. Romera Ramirez
    CIEMAT, Madrid
  • SF. Feher, R. H. Flora
    Fermilab, Batavia, Illinois
 
  The LHC is a complex machine requiring more than 7400 superconducting corrector magnets distributed along a circumference of 26.7 km. These magnets are powered in 1380 different electrical circuits with currents ranging from 60 A up to 600 A. Among the corrector circuits the 600 A corrector magnets form the most diverse and differentiated magnet circuits. About 60000 high current connections had to be made. A minor fault in a circuit or one of the superconducting connections would have severe consequences for the accelerator operation. All magnets are wound from various types of Nb-Ti superconducting strands, and many contain resistors to by-pass the current in case of the transition to the normal conducting state in case of a quench, and hence reduce the hot spot temperature. In this paper the performance of these magnet circuits is presented, focussing on the quench current and quench behaviour of the magnets. Quench detection and the performance of the electrical interconnects will be dealt with. The results as measured on the entire circuits will be compared to the test results obtained during the reception tests of the individual magnets.