A   B   C   D   E   F   G   H   I   J   K   L   M   N   O   P   Q   R   S   T   U   V   W   X   Y   Z  

Milloch, M. M.

Paper Title Page
MOPC008 The Impact of PSK Timing on Energy Stability of e-Beam at FERMI@ELETTRA 82
 
  • G. D'Auria, P. Delgiusto, M. M. Milloch, C. Serpico, D. Wang
    ELETTRA, Basovizza, Trieste
 
  The existing linac sections S1-S7 at ELETTRA will be upgraded for the FERMI@ELETTRA FEL project. These seven sections are 3/4 π-mode backward traveling wave (BTW) constant-impedance structures, powered by 45-MW klystrons (Thales TH 2132A) and with a SLED system to increase the RF peak power. Because of the strict requirement on the pulse-to-pulse beam energy stability (<0.1%) of the FERMI@ELETTRA project, the impact of phase shift keying (PSK), the timing of phase flipping, on beam energy needs to be revisited and evaluated. Here the results obtained with a simulation model built up by use of MATLAB simulink are present and discussed.  
WEPC071 Installation and Commissioning of the 100 MeV Preinjector Linac of the New Elettra Injector 2160
 
  • G. D'Auria, P. Borsi, A. Carniel, P. Delgiusto, O. Ferrando, A. Franceschinis, M. M. Milloch, A. Milocco, F. Pribaz, N. Sodomaco, M. Stefanutti, L. Veljak, D. Wang
    ELETTRA, Basovizza, Trieste
  • L. Picardi, C. Ronsivalle
    ENEA C. R. Frascati, Frascati (Roma)
 
  A new full energy injector has been installed and commissioned at Sincrotrone Trieste, the Italian Synchrotron Light Source Facility in Trieste. It consists of a 100 MeV Preinjector Linac (PL) followed by a 2.5 GeV Booster Synchrotron (BS), that will fill the Elettra Storage Ring (SR) with 2.0 GeV and 2.4 GeV electrons. Here a complete description of the preinjector linac and its characterization in terms of beam parameters will be presented and discussed.