MOPC103 Short Circuit Tests: First Step of LHC Hardware Commissioning Completion 304
 
  • B. Bellesia, E. Barbero-Soto, F. Bordry, M. P. Casas Lino, G.-J. Coelingh, G. Cumer, K. Dahlerup-Petersen, J.-C. Guillaume, J. Inigo-Golfin, V. Montabonnet, D. Nisbet, M. Pojer, R. Principe, F. Rodriguez-Mateos, R. I. Saban, R. Schmidt, H. Thiesen, A. Vergara-Fernández, M. Zerlauth
    CERN, Geneva
  • A. Castaneda, I. Romera Ramirez
    CIEMAT, Madrid
 
  The Large Hadron Collider operation relies on 1232 superconducting dipoles with a field of 8.33T and 400 superconducting quadrupoles with a strength of 220 T/m powered at 12kA, operating in superfluid He at 1.9K. For dipoles and quadrupoles as well as for many other magnets more than 1700 power converters are necessary to feed the superconducting circuits. Between October 2005 and September 2007 the so-called short circuit tests were carried-out in the 15 underground areas where the power converters of the superconducting circuits are located. The tests were aimed at the qualification of the normal conducting components of the circuits: the power converters, the normal conducting DC cables between the power converters and the LHC cryostat, the interlocks and energy extraction systems. In addition, the correct functioning of the infrastructure systems (AC distribution, water and air cooling, control system) were validated. The final validation test for each underground area was the powering of all converters at ultimate current during 24h. This approach highlighted a few problems that were solved long before the beginning of magnet commissioning and beam operation.