WEPD040 Outcome of the Commissioning of the Readout and Actuation Channels for the Cryogenics of the LHC 2500
 
  • G. Fernandez Penacoba, C. Balle, J. Casas-Cubillos, J. De La Gama, P. Gomes, E. Gousiou, N. Jeanmonod, A. Lopez Lorente, E. Molina Marinas, A. Suraci, N. Vauthier
    CERN, Geneva
 
  The installation of the Large Hadron Collider (LHC) at CERN has been completed and its commissioning is now in progress. The LHC is the largest cryogenic installation ever built. It includes 1700 superconducting magnets, a cryogenic distribution line (QRL) running parallel to the accelerator, 52 electrical distribution feedboxes (DFB) supporting the superconducting current leads that supply power to the magnets circuits, and 16 superconducting RF accelerating cavities. For its operation more than 10 000 sensors and actuators are required. The commissioning of this instrumentation includes the validation of both hardware (installed sensors, cabling, front-end electronics, communication field-buses) and software (databases extraction, programmable logic controllers programs, supervision coherence). At present point, having provided the cryogenic instrumentation for the operation in half of the LHC, more than 95% of the channels are working within specifications. This paper presents the commissioning strategy, tracking policy, and performance results after commissioning of the cryogenic instrumentation for the LHC.