MOPCH129 Status of the SNS Beam Power Upgrade Project 345
 
  • S. Henderson, A.V. Aleksandrov, D.E. Anderson, S. Assadi, I.E. Campisi, F. Casagrande, M.S. Champion, R.I. Cutler, V.V. Danilov, G.W. Dodson, D.A. Everitt, J. Galambos, J.R. Haines, J.A. Holmes, N. Holtkamp, T. Hunter, D.-O. Jeon, S.-H. Kim, D.C. Lousteau, T.L. Mann, M.P. McCarthy, T. McManamy, G.R. Murdoch, M.A. Plum, B.R. Riemer, M.P. Stockli, D. Stout, R.F. Welton
    ORNL, Oak Ridge, Tennessee
 
  The baseline Spallation Neutron Source (SNS) accelerator complex, consisting of an H- injector, a 1 GeV linear accelerator, an accumulator ring and associated transport lines, will provide a 1 GeV, 1.44 MW proton beam to a liquid mercury target for neutron production. Upgrades to the SNS accelerator and target systems to increase the beam power to at least 2 MW, with a design goal of 3 MW, are in the planning stages. The increased SNS beam power can be achieved primarily by increasing the peak H- ion source current from 38 mA to 59 mA, installing additional superconducting cryomodules to increase the final linac beam energy to 1.3 GeV, and modifying injection and extraction hardware in the ring to handle the increased beam energy. The mercury target power handling capability will be increased to 2 MW or greater by i) mitigating cavitation damage to the target container through improved materials/surface treatments, and introducing a fine dispersion of gas bubbles in the mercury, and ii) upgrading the proton beam window, inner reflector plug and moderators. The upgrade beam parameters will be presented and the required hardware modifications will be described.  
MOPCH131 SNS Ring Commissioning Results 351
 
  • M.A. Plum, A.V. Aleksandrov, S. Assadi, W. Blokland, I.E. Campisi, P. Chu, S.M. Cousineau, V.V. Danilov, C. Deibele, G.W. Dodson, J. Galambos, M. Giannella, S. Henderson, J.A. Holmes, D.-O. Jeon, S.-H. Kim, C.D. Long, T.A. Pelaia, T.J. Shea, A.P. Shishlo, Y. Zhang
    ORNL, Oak Ridge, Tennessee
 
  The Spallation Neutron Source (SNS) comprises a 1.5-MW, 60-Hz, 1-GeV linac, an accumulator ring, associated beam lines, and a spallation neutron target. Construction began in 1999 and the project is on track to be completed in June 2006. By September 2005 the facility was commissioned up through the end of the superconducting linac, and in January 2006 commissioning began on the High Energy Beam Transport beam line, the accumulator ring, and the Ring to Target Beam Transport beam line up to the Extraction Beam Dump. In this paper we will discuss early results from ring commissioning including a comparison of achieved vs. design beam machine parameters and the maximum beam intensity achieved to date.