Author: Poggi, M.
Paper Title Page
TUP09 Diagnostic Tool and Instrumentation for Handling 50 kW Beam Power 184
 
  • P. Antonini, E. Boratto, A. Calore, D. Campo, J. Esposito, A. Lombardi, M. Maggiore, M. Poggi, L. Pranovi
    INFN/LNL, Legnaro (PD), Italy
 
  The SPES facility is entered the commissioning phase and the 70 MeV cyclotron is delivering the proton beams at the maximum power permitted. The INFN team has developed additional beam instrumentation in order to stop the particles at different power allowing the tuning of the beamline and to check the particles losses during the transport. In particular, a beam dumper able to stop up to 55kW beam power has been constructed and tested as well as the beam loss monitor system by INFN team. Here we present the status of the beam instrumentations supplied by INFN and the results achieved during the test with the beam.  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)