Paper | Title | Page |
---|---|---|
TUAA02 | Commissioning of the SRF Linac for ARIEL | 457 |
|
||
This paper is reporting commissioning results for the SRF linac of ARIEL facility at TRIUMF. The paper is focused on the SRF challenges: cavity design and performance, ancillaries design and preparation, cryomodule design and performance, RF system and final beam test results. | ||
![]() |
Slides TUAA02 [4.004 MB] | |
Export • | reference for this paper to ※ BibTeX, ※ LaTeX, ※ Text, ※ RIS/RefMan, ※ EndNote (xml) | |
TUPB011 | HPRF Transmission Componenets Study and Distribution in TRIUMF E-Linac | 557 |
|
||
TRIUMF e-lianc was commissioning last September for the first stage. High power rf systems were in operation stable. Two 300 kW klystrons along with the key waveguide components were tested before feeding rf power into 1.3 GHz 9-cell superconducting cavities. The rf high power variable divider and 360 degree waveguide phase shifters are working successfully. The simulations on different waveguide structures for the power dividers, phase shifters have been studied. The comparisons of the calculation results are reported in the paper. The rf signal level tests of the components and waveguide distribution systems will also be present in this paper. | ||
Export • | reference for this paper to ※ BibTeX, ※ LaTeX, ※ Text, ※ RIS/RefMan, ※ EndNote (xml) | |