TUP225 Overview of Recent Studies and Modifications Being Made to RHIC to Mitigate the Effects of a Potential Failure to the Helium Distribution System 1241
 
  • J.E. Tuozzolo, D. Bruno, A. Di Lieto, G. Heppner, R. Karol, E.T. Lessard, C.J. Liaw, G.T. McIntyre, C. Mi, J. Reich, J. Sandberg, S.K. Seberg, L. Smart, T.N. Tallerico, R. Than, C. Theisen, R.J. Todd, R. Zapasek
    BNL, Upton, Long Island, New York, USA
 
  Funding: Work supported by Brookhaven Science Associates, LLC under Contract No. DE-AC02-98CH10886 with the U.S. Department of Energy.
In order to cool the superconducting magnets in RHIC, its helium refrigerator distributes 4.5 K helium throughout the tunnel via a series of distribution and return lines. The worst case for failure would be a release from the magnet distribution line, which operates at 3.5 to 4.5 atmospheres and contains the energized magnet bus. Should the bus insulation system fail or an electrical connection open, there is the potential for releasing up to 70 MJoules of stored energy. Studies were done to determine release rate of the helium and the resultant reduction in O2 concentration in the RHIC tunnel and service buildings. Equipment and components were also reviewed for reliability and the effects of 10 years of operations. Modifications were made to reduce the likelihood of failure and to reduce the amount of helium gas that could be released into tunnels and service buildings while personnel are present. This paper describes the issues reviewed, the steps taken, and remaining work to be done to reduce the hazards.
 
 
THP006 Status of High Current R&D Energy Recovery Linac at Brookhaven National Laboratory 2148
 
  • D. Kayran, Z. Altinbas, D.R. Beavis, I. Ben-Zvi, R. Calaga, D.M. Gassner, H. Hahn, L.R. Hammons, A.K. Jain, J.P. Jamilkowski, N. Laloudakis, R.F. Lambiase, D.L. Lederle, V. Litvinenko, G.J. Mahler, G.T. McIntyre, W. Meng, B. Oerter, D. Pate, D. Phillips, J. Reich, T. Roser, C. Schultheiss, B. Sheehy, T. Srinivasan-Rao, R. Than, J.E. Tuozzolo, D. Weiss, W. Xu, A. Zaltsman
    BNL, Upton, Long Island, New York, USA
 
  An ampere-class 20 MeV superconducting energy recovery linac (ERL) is under construction at Brookhaven National Laboratory (BNL) for testing of concepts relevant for high-energy coherent electron cooling and electron-ion colliders. One of the goals is to demonstrate an electron beam with high charge per bunch (~5 nC) and low normalized emittance (~5 mm-mrad) at an energy of 20 MeV. A flexible lattice for the ERL loop provides a test bed for investigating issues of transverse and longitudinal instabilities and diagnostics for CW beam. A superconducting 703 MHz RF photo-injector is considered as an electron source for such a facility. We will start with a straight pass (gun/cavity/beam stop) test for gun performance studies. Later, we will install and test a novel injection line concept for emittance preservation in a lower-energy merger. Here we present the status and our plans for construction and commissioning of this facility.