MOP009 Status and Plans for a SRF Accelerator Test Facility at Fermilab 118
 
  • J.R. Leibfritz, R. Andrews, K. Carlson, B. Chase, M.D. Church, E.R. Harms, A.L. Klebaner, M.J. Kucera, S.L. Lackey, A. Martinez, S. Nagaitsev, L.E. Nobrega, J. Reid, M. Wendt, S.J. Wesseln
    Fermilab, Batavia, USA
  • P. Piot
    Northern Illinois University, DeKalb, Illinois, USA
 
  Funding: Operated by Fermi Research Alliance, LLC, under Contract No. DE-AC02-07CH11359 with the U.S. Department of Energy
A superconducting RF accelerator test facility is being constructed at Fermilab. The existing New Muon Lab (NML) building is being converted for this facility. The accelerator will consist of an electron gun, injector, beam acceleration section consisting of 3 TTF-type or ILC-type cryomodules, multiple downstream beamlines for testing diagnostics and conducting various beam tests, and a high power beam dump. When completed, it is envisioned that this facility will initially be capable of generating a 810 MeV electron beam with ILC beam intensity. Expansion plans of the facility are underway that will provide the capability to upgrade the accelerator to a total beam energy of 1.5 GeV. In addition to testing accelerator components, this facility will be used to test RF power equipment, instrumentation, LLRF and controls systems for future SRF accelerators such as the ILC and Project-X. This paper describes the current status and overall plans for this facility.
 
 
TUP076 First High Power Pulsed Tests of a Dressed 325 MHz Superconducting Single Spoke Resonator at Fermilab 964
 
  • R.L. Madrak, J. Branlard, B. Chase, C. Darve, P.W. Joireman, T.N. Khabiboulline, A. Mukherjee, T.H. Nicol, E. Peoples-Evans, D.W. Peterson, Y.M. Pischalnikov, L. Ristori, W. Schappert, D.A. Sergatskov, W.M. Soyars, J. Steimel, I. Terechkine, V. Tupikov, R.L. Wagner, R.C. Webber, D. Wildman
    Fermilab, Batavia, USA
 
  In the recently commissioned superconducting RF cavity test facility at Fermilab (SCTF), a 325 MHz, β=0.22 superconducting single-spoke resonator (SSR1) has been tested for the first time with its input power coupler. Previously, this cavity had been tested CW with a low power, high Qext test coupler; first as a bare cavity in the Fermilab Vertical Test Stand and then fully dressed in the SCTF. For the tests described here, the design input coupler with Qext ~ 106 was used. Pulsed power was provided by a Toshiba E3740A 2.5 MW klystron.  
 
TUP086 Microphonics control for Project X 988
 
  • W. Schappert, S. Barbanotti, J. Branlard, G.I. Cancelo, R.H. Carcagno, M.S. Champion, B. Chase, I.G. Gonin, A.L. Klebaner, D.F. Orris, T.J. Peterson, Y.M. Pischalnikov, L. Ristori, N. Solyak, V.P. Yakovlev
    Fermilab, Batavia, USA
 
  Funding: Work is supported by the U.S. Department of Energy
The proposed multi-MW Project X facility at Fermilab will employ cavities with bandwidths as narrow as 20 Hz. This combination of high RF power with narrow bandwidths combined requires careful attention to detuning control if these cavities are to be operated successfully. Detuning control for Projects X will require a coordinated effort between the groups responsible for various machine subsystems. Considerable progress in this area has been made over the past year.
 
 
WEP094 Space Charge Measurements with a High Intensity Bunch at the Fermilab Main Injector 1648
 
  • K. Seiya, B. Chase, J.E. Dey, P.W. Joireman, I. Kourbanis
    Fermilab, Batavia, USA
  • A. Yagodnitsyna
    NSU, Novosibirsk, Russia
 
  Fermilab Main Injector will be required to operate with 3 times higher bunch intensity than today for Project X. The plan to study the space charge effects at the injection energy with intense bunches will be discussed.