Author: Adamson, P.
Paper Title Page
TUXB3 700 kW Main Injector Operations for NOvA at FNAL 1286
 
  • P. Adamson
    Fermilab, Batavia, Illinois, USA
 
  Following a successful career as an antiproton storage and cooling ring, the Fermilab Recycler was repurposed as a proton stacker as part of the NOvA project, in order to increase the maximum NuMI beam power from 400 kW to 700 kW. Using the Recycler to prepare beam for acceleration in the Main Injector, we have been able to increase the beam power delivered to NuMI to a sustained weekly average in excess of 400 kW and a best hourly average of 482.8 kW. I discuss the commissioning progress to date, and describe the remaining steps along the way to achieving the 700 kW design goal.  