Author: Polat, E.Ç.
Paper Title Page
MOPRI045 Beam Diagnostics E-GUN Test Stand at TARLA 704
 
  • Ç. Kaya, A.A. Aksoy, A. Aydin, V. Karakilic, Ö. Karslı, E. Kazancı, B. Koc, S. Kuday, E.Ç. Polat, I. Sara, M. Yildiz
    Ankara University, Accelerator Technologies Institute, Golbasi / Ankara, Turkey
  • S. Özkorucuklu
    Istanbul University, Istanbul, Turkey
 
  Funding: Work supported by Turkish State Planning Organization (Grant No: DPT2006K-120470)
Turkish Accelerator and Radiation Laboratory in Ankara (TARLA) facility, which is essentially proposed to generate oscillator mode FEL in 3-250 microns wavelengths range, will consist of totally normal conducting injector system with 250 keV beam energy, two superconducting RF accelerating modules in order to accelerate the beam 15-40 MeV. Continuous wave (CW) electron beam will provided by TARLA thermionic electron gun (E-GUN). Various aspects of the Thermionic EGUN test stand to deliver the necessary electron beam in terms of bunch charge, current, energy, emittance and profile for the beam diagnostic will be discussed. Primarily measurements results of electron beam energy loss and transverse orbit will be shown as well as beam image and shape measurements.
On behalf of TARLA Collaboration
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-MOPRI045  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPRI044 Final Structure and Design Parameters of TARLA RF System 2577
 
  • Ö. Karslı, A.A. Aksoy, Ç. Kaya, İ.B. Koc, E.Ç. Polat, Ö. Yavaş
    Ankara University, Accelerator Technologies Institute, Golbasi / Ankara, Turkey
  • M. Doğan
    Dogus University, Istanbul, Turkey
  • S. Özkorucuklu
    Istanbul University, Istanbul, Turkey
 
  Funding: Work supported by Turkish Ministry of Development (Grant No: DPT2006K-120470)
Turkish Accelerator and Radiation Laboratory in Ankara (TARLA) is an oscillator mode IR-FEL facility which is under construction since 2011. ELBE licensed superconducting modules housing TESLA RF cavities have been manufacturing for one year and the first module will be delivered in 2015. He Cryogenic System has also started to be manufacturing at similar time with the accelerator structures. It will be delivered in 2014. High Power RF amplifiers are started to tender procedures and delivery time is planning as 2015. The installation of high power transmission lines have to be completed at the same time with the delivery date of HPRF amplifiers to test the cavities and amplifiers. In this study, the final structural design of high power RF transmission lines and design parameters of RF amplifiers for TARLA is discussed.
On behalf of TARLA Collaboration, www.tarla.org.tr
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-WEPRI044  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)