Author: Bregliozzi, G.
Paper Title Page
MOPME074 High Voltage Performance of the Beam Screen of the LHC Injection Kicker Magnets 541
 
  • M.J. Barnes, P. Adraktas, G. Bregliozzi, S. Calatroni, P. Costa Pinto, H.A. Day, L. Ducimetière, V. Gomes Namora, T. Kramer, V. Mertens, M. Taborelli
    CERN, Geneva, Switzerland
 
  The LHC injection kicker magnets include beam screens to shield the ferrite yokes against wakefields resulting from the high intensity beam. The screening is provided by conductors lodged in the inner wall of a ceramic support tube. The design of the beam screen has been upgraded to overcome limitations and permit LHC operation with increasingly higher bunch intensity and short bunch lengths: the new design also significantly reduces the electric field associated with the screen conductors, decreasing the probability of electrical breakdown. The high voltage conditioning process for the upgraded kicker magnets is presented and discussed. In addition a test setup has been utilized to study flashover, on the inner wall of the ceramic tube, as a function of both applied voltage and vacuum pressure: results from the test setup are presented.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-MOPME074  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPRO027 First Beam Background Simulation Studies at IR1 for High Luminosity LHC 1074
 
  • R. Kwee-Hinzmann, S.M. Gibson
    JAI, Egham, Surrey, United Kingdom
  • G. Bregliozzi, R. Bruce, F. Cerutti, L.S. Esposito, R. Kersevan, A. Lechner, N.V. Shetty
    CERN, Geneva, Switzerland
  • S.M. Gibson
    Royal Holloway, University of London, Surrey, United Kingdom
 
  In the High-Luminosity Large Hadron Collider (HL-LHC) Project, the LHC will be significantly upgraded to attain a peak luminosity of up to 8.5 × 1034 cm-2s-1, thus almost an order of magnitude higher compared to the nominal machine configuration in ATLAS at IP1 and CMS at IP5. In the view of a successful machine setup as well as a successful physics programme, beam induced background studies at IP1 were performed to investigate sources of particle fluxes to the experimental area. In particular as a start of the study, two sources forming the major contributions were simulated in detail: the first one considers inelastic interactions from beam particles hitting tertiary collimators, the second one from beam interactions with residual gas-molecules in the vacuum pipe close by the experiment, referred to as beam-halo and local beam-gas, respectively. We will present these first HL-LHC background studies based on SixTrack and FLUKA simulations, highlighting the simulation setup for the design case in the HL-LHC scenario. Results of particle spectra entering the ATLAS detector region are presented for the latest study version of HL-LHC machine layout (2013).  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-TUPRO027  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPME033 Search for New e-cloud Mitigator Materials for High Intensity Particle Accelerators 2332
 
  • R. Cimino, S.T. O'connor, A.L. Romano
    INFN/LNF, Frascati (Roma), Italy
  • V. Baglin, G. Bregliozzi, R. Cimino
    CERN, Geneva, Switzerland
  • M.R. Masullo
    INFN-Napoli, Napoli, Italy
  • S. Petracca, A. Stabile
    INFN-Salerno, Baronissi, Salerno, Italy
 
  Electron cloud is an ubiquitous effect in positively charged particle accelerators and has been observed to induce unwanted detrimental impacts on beam quality, stability, vacuum etc. A great effort has been recently devoted to the search of new material morphology and/or coatings which can intrinsically mitigate beam instabilities deriving from electron cloud effects. In this context, we present some characterization of Cu foams, available from the market, and their qualification in terms of their vacuum behavior, impedance, secondary electron yield, gas desorption etc. More experimental effort is required to finally qualify foams as a mature technology to be integrated in accelerator environments. But, our preliminary results suggests that, when compatible with geometrical constrains, Cu foams can be utilized when low desorption yields are required and as e-cloud moderator in future particles accelerators.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-WEPME033  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPME041 Vacuum Acceptance Tests for the UHV Room Temperature Vacuum System of the LHC during LS1 2357
 
  • G. Cattenoz, V. Baglin, G. Bregliozzi, D. Calegari, P. Chiggiato, J.E. Gallagher, A. Marraffa
    CERN, Geneva, Switzerland
 
  During the CERN Large Hadron Collider (LHC) first long shut down (LS1), a large number of vacuum tests are carried out on consolidated or newly fabricated pieces of equipment. In such a way, the vacuum compatibility is assessed before installation in the UHV system of the LHC. According to the equipment’s nature, the vacuum acceptance tests consist in functional checks, leak tests, outgassing rate measurements, evaluation of contaminants by Residual Gas Analysis (RGA), pumping speed measurements, and qualification of the sticking probability of Non-Evaporable-Getter coating. In this paper, the methods used for the tests and the acceptance criteria are described. A summary of the measured vacuum characteristics for the tested components is also given.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-WEPME041  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPME042 The LHC Vacuum Pilot Sectors Project 2360
 
  • B. Henrist, V. Baglin, G. Bregliozzi, P. Chiggiato
    CERN, Geneva, Switzerland
 
  The operation of the CERN Large Hadron Collider (LHC) at nominal beam parameters is expected for the next years (2015). Increased synchrotron-radiation stimulated-desorption and electron-cloud build-up are expected. A deep understanding of the interactions between the proton beams and the beampipe wall is mandatory to control the anticipated beam-induced pressure rise. A Vacuum Pilot Sector (VPS) has been designed to monitor the performance of the vacuum system with time. The VPS is installed along a double LHC room temperature vacuum sector (18 m long, 80 mm inner diameter beam pipes) and includes 8 standard modules, 1.4 m long each. Such modules are equipped with residual gas analysers, Bayard-Alpert gauges, photon and electron flux monitors, etc. The chosen modular approach opens the possibility of studying different configurations and implementing future modifications. This contribution will describe the apparatus, the control system designed to drive measurements and possible applications during the next LHC operational phase.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-WEPME042  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPME044 LHC Experimental Beam Pipe Upgrade during LS1 2366
 
  • G. Lanza, V. Baglin, G. Bregliozzi, P. Chiggiato
    CERN, Geneva, Switzerland
 
  The LHC experimental beam pipes are being improved during the ongoing long shutdown 1 (LS1). Several vacuum chambers have been tested and validated before their installation inside the detectors. The validation tests include: leak tightness, ultimate vacuum pressure, material outgassing rate, and residual gas composition. NEG coatings are assessed by hydrogen sticking probability measurement with the help of Monte Carlo simulations. In this paper the motivation for the beam pipe upgrade, the validation tests of the components and the results are presented and discussed.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-WEPME044  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPME045 Assessment of New Components to be Integrated in the LHC Room Temperature Vacuum System 2369
 
  • G. Bregliozzi, V. Baglin, P. Chiggiato
    CERN, Geneva, Switzerland
 
  Integration of new equipment in the long straight sections (LSS) of the LHC must be compatible with the TiZrV non-evaporable getter thin film that coats most of the 6-km-long room-temperature beam pipes. This paper focus on two innovative accelerator devices to be installed in the LSS during the long shutdown 1 (LS1): the beam gas vertex (BGV) and a beam bending experiment using crystal collimator (LUA9). The BGV necessitates a dedicated pressure bump, generated by local gas injection, in order to create the required rate of inelastic beam-gas interactions. The LAU9 experiments aims at improving beam cleaning efficiency with the use of a crystal collimator. New materials like fibre optics, piezoelectric components, and glues are proposed in the original design of the two devices. The integration feasibility of these set-ups in the LSS is presented. In particular outgassing tests of special components, X-rays photoelectron spectroscopy, analysis of NEG coating behaviour in presence of glues during bake-out, and pressure profile simulations will be presented.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-WEPME045  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPME047 CERN Vacuum System Activities during the Long Shutdown 1: the LHC Beam Vacuum 2375
 
  • V. Baglin, G. Bregliozzi, P. Chiggiato, J.M. Jimenez, G. Lanza
    CERN, Geneva, Switzerland
 
  After the Long Shutdown 1 (LS1) and the consolidation of the magnet bus bars, the CERN Large Hadron Collider (LHC) will operate with nominal beam parameters. Larger beam energy, beam intensities and luminosity are expected. Despite the very good performance of the beam vacuum system during the 2010-12 physics run (Run 1), some particular areas require attention for repair, consolidation and upgrade. Among the main activities, a large campaign aiming at the repair of the RF bridges of some vacuum modules is conducted. Moreover, consolidation of the cryogenic beam vacuum systems with burst disk for safety reasons is implemented. In addition, NEG cartridges, NEG coated inserts and new instruments for the vacuum system upgrade are installed. Besides these activities, repair, consolidation and upgrades of other beam equipment such as collimators, kickers and beam instrumentations are carried out. In this paper, the motivation and the description for such activities, together with the expected beam vacuum performance after LS1, are described in detail.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-WEPME047  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
WEPME049 Coupled Simulations of the Synchrotron Radiation and Induced Desorption Pressure Profiles for the HiLumi-LHC Triplet Area and Interaction Points 2381
 
  • R. Kersevan, V. Baglin, G. Bregliozzi
    CERN, Geneva, Switzerland
 
  The HiLumi-LHC machine upgrade has officially started as an approved LHC project (see dedicated presentations at this conference on the subject). One important feature of the upgrade is the installation of very high-gradient triplet magnets for focusing the beams at the collision points of the two high-luminosity detectors ATLAS and CMS. Other important topics are new superconducting D1 magnets, installation of crab cavities, and re-shuffling of the dispersion suppression area. Based on the current magnetic lattice set-up and beam orbits, a detailed study of the emission of synchrotron radiation (SR) and related photon-induced desorption (PID) has been carried out. A significant amount of SR photons are generated by the two off-axis beams in the common vacuum chamber of the triplet area, about 57 m in length. Ray-tracing Montecarlo codes SYNRAD+ and Molflow+ have been employed in this study. The related PID pressure profiles will be shown, together with simulations using the code VASCO for the analysis of beam losses and background in the detectors, including electron cloud effects.
(*) The HiLumi LHC Design Study is partly funded by the European Commission within the Framework Programme 7 Capacities Specific Programme, Grant Agreement 284404
 
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-WEPME049  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
THPME175 A Beam Gas Vertex Detector for Beam Size Measurement in the LHC 3680
 
  • P. Hopchev, V. Baglin, C. Barschel, E. Bravin, G. Bregliozzi, N. Chritin, B. Dehning, M. Ferro-Luzzi, C. Gaspar, M. Giovannozzi, R. Jacobsson, L.K. Jensen, O.R. Jones, N.J. Jurado, V. Kain, M. Kuhn, B. Luthi, P. Magagnin, R. Matev, N. Neufeld, J. Panman, M.N. Rihl, V. Salustino Guimaraes, B. Salvant, R. Veness, E. van Herwijnen
    CERN, Geneva, Switzerland
  • A. Bay, F. Blanc, S. Gianì, G.J. Haefeli, T. Nakada, B. Rakotomiaramanana, O. Schneider, M. Tobin, Q.D. Veyrat, Z. Xu
    EPFL, Lausanne, Switzerland
  • R. Greim, W. Karpinski, T. Kirn, S. Schael, G. Schwering, M. Wlochal, A. von Dratzig
    RWTH, Aachen, Germany
  • R. Matev
    Sofia University St. Kliment Ohridski, Faculty of Physics, Sofia, Bulgaria
 
  The Beam Gas Vertex (BGV) detector is foreseen as a possible non-invasive beam size measurement instrument for the LHC and its luminosity upgrade. This technique is based on the reconstruction of beam gas interaction vertices, where the charged particles produced in inelastic beam gas interactions are measured with high-precision tracking detectors. The design studies and expected performance of the currently developed BGV prototype will be presented with an overview given of the associated vacuum, detector, and readout systems. A brief description will be given of the BGV Monte Carlo simulation application, which is based on the LHCb computing framework (Gaudi) and allows simulation studies to be performed and online event reconstruction algorithms to be developed.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-THPME175  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)