TUPRO007 LS1 “First Long Shutdown of LHC and its Injector Chains” 1010
 
  • K. Foraz, S. Baird, M.B.M. Barberan Marin, M. Bernardini, J. Coupard, N. Gilbert, D. Hay, S. Mataguez, D.J. Mcfarlane
    CERN, Geneva, Switzerland
 
  The LHC and its injectors were stopped in February 2013, in order to maintain, consolidate and upgrade the different equipment of the accelerator chain, with the goal of achieving LHC operation at the design energy of 14 TeV in the centre-of-mass. Prior to the start of this Long Shutdown (LS1), a major effort of preparation was performed in order to optimize the schedule and the use of resources across the different machines, with the aim of resuming LHC physics in early 2015. The rest of the CERN complex will restart beam operation in the second half of 2014. This paper presents the schedule of LS1, describes the organizational set-up for the coordination of the works, the main activities, the different main milestones, which have been achieved so far, and the decisions taken in order to mitigate the issues encountered.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-TUPRO007  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
TUPRO012 Optimisation and Implementation of the R2E Shielding and Relocation Mitigation Measures at the LHC during the LS1 1027
 
  • A.-L. Perrot, O. Andujar, M.B.M. Barberan Marin, M. Brugger, J.-P. Corso, K. Foraz, M. Jeckel, M. Lazzaroni, B. Lefort, B. Mikulec, Y. Muttoni
    CERN, Geneva, Switzerland
 
  In the framework of the Radiation to Electronics (R2E) project, important mitigation actions are being implemented in the LHC during the first Long Shutdown (LS1) to reduce the Single Event Error (SEE) occurrence in standard electronics present in much of the equipment installed in LHC underground areas. Recent simulations have motivated additional actions to be performed in Point 4, in addition to those already scheduled in Points 1, 5, 7 and 8. This paper presents the organisation process carried out during LS1 to optimise the implementation of the R2E mitigation activities. It reports the challenges linked to civil engineering and to safe room relocation in Points 5 and 7. It highlights the reactivity needed to face the new mitigation requirements to be implemented in Point 4 before the end of LS1. It presents the advancement status of the R2E mitigation activities in the different LHC points with the main concerns and impact with the overall LHC LS1 planning.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2014-TUPRO012  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)