MOPEA080 Status of the NSLS-II Injector 273
 
  • T.V. Shaftan, A. Blednykh, E.B. Blum, W.X. Cheng, J. Choi, L.R. Dalesio, M.A. Davidsaver, J.H. De Long, R.P. Fliller, G. Ganetis, F. Gao, A. Goel, W. Guo, K. Ha, R. Heese, H.-C. Hseuh, M.P. Johanson, B.N. Kosciuk, S. Kowalski, S.L. Kramer, Y. Li, W. Louie, S. Ozaki, D. Padrazo, J. Rose, S. Seletskiy, S.K. Sharma, G. Shen, O. Singh, V.V. Smaluk, Y. Tian, K. Vetter, W.H. Wahl, G.M. Wang, F.J. Willeke, X. Yang, L.-H. Yu, P. Zuhoski
    BNL, Upton, Long Island, New York, USA
 
  We discuss the current status and plans for developing the NSLS-II injector. The latter consists of a 200 MeV linac, a 3-GeV booster, transport lines and the storage ring injection straight section. The system design and installation are complete. Last year we concluded 200-MeV linac commissioning and are planning to commission the 3 GeV booster during summer of 2013.