WEPPC088 Standardization of CEBAF 12 GeV Upgrade Cavity Testing 2420
 
  • T. Bass, G.K. Davis, C. Grenoble, M. Stirbet
    JLAB, Newport News, Virginia, USA
 
  Funding: Authored by Jefferson Science Associates, LLC under U.S. DOE Contract No. DE-AC05-06OR23177.
CEBAF 12GeV upgrade project includes 80 new 7-cell cavities to form 10 cryomodules. Each cavity underwent RF qualification at 2 Kelvin using a high power accelerating gradient test and an HOM survey in JLab’s Vertical Testing Area (VTA) before cavity string assembly. In order to ensure consistently high quality data, updated cavity testing procedures and analysis were implemented and used by a group of 10 VTA operators. For high power tests, a cavity testing procedure was developed and used in conjunction with a LabVIEW program to collect the test data. Additionally while the cavity was at 2K, an HOM survey was performed using a network analyzer and a combination of Excel and Mathematica programs. Data analysis was standardized and an online logbook, Pansophy, was used for data storage and mining. The Pansophy system allowed test results to be easily summarized and searchable across all cavity tests. In this presentation, the CEBAF 12GeV upgrade cavity testing procedure, method for data analysis, and results reporting results will be discussed.
 
 
WEPPC089 SRF Cavity Performance Overview for the 12 GeV Upgrade 2423
 
  • A. Burrill, G.K. Davis, C.E. Reece, A.V. Reilly, M. Stirbet
    JLAB, Newport News, Virginia, USA
 
  Funding: Authored by Jefferson Science Associates, LLC under U.S. DOE Contract No. DE-AC05-06OR23177.
The CEBAF accelerator, a recirculating CW electron accelerator that is currently operating at Jefferson Laboratory, is in the process of having 10 new cryomodules installed to allow for the maximum beam energy to be increased from 6 GeV to 12 GeV. This upgrade required the fabrication, processing and RF qualification of 80, seven cell elliptical SRF cavities, a process that was completed in February 2012. The RF performance achieve in the vertical testing dewars has exceeded the design specification by ~25% and is a testament to the cavity design and processing cycle that has been implemented. This paper will provide a summary of the cavity RF performance in the vertical tests, as well as review the overall cavity processing cycle and duration for the project.
 
 
WEPPR096 Recirculating Beam Breakup Study for the 12 GeV Upgrade at Jefferson Lab 3162
 
  • I. Shin, S. Ahmed, R.M. Bodenstein, S.A. Bogacz, T. Satogata, M. Stirbet, H. Wang, Y. Wang, B.C. Yunn
    JLAB, Newport News, Virginia, USA
  • I. Shin
    University of Connecticut, Storrs, Connecticut, USA
 
  Two new high gradient C100 cryostats with a total of 16 new cavities were installed at the end of the CEBAF south linac during the 2011 summer shutdown as part of the 12 GeV upgrade project at Jefferson Lab. We ran recirculating beam breakup (BBU) study in November 2011 to evaluate CEBAF low energy performance, measure transport optics, and evaluate BBU thresholds due to higher order modes (HOMs) in these cavities. This paper discusses the experiment setup, cavity measurements, machine setup, optics measurements, and lower bounds on existing CEBAF C100 BBU thresholds established by this experiment.