MOOAB03 FACET First Beam Commissioning 46
 
  • G. Yocky, C.I. Clarke, W.S. Colocho, F.-J. Decker, M.J. Hogan, N. Lipkowitz, J. Nelson, P.M. Schuh, J.T. Seeman, J. Sheppard, H. Smith, T.J. Smith, M. Stanek, Y. Sun, J.L. Turner, M.-H. Wang, S.P. Weathersby, G.R. White, U. Wienands, M. Woodley
    SLAC, Menlo Park, California, USA
 
  Funding: Work supported by U.S. Department of Energy, Contract DE-AC02-76SF00515.
The FACET (Facility for Advanced aCcelerator Experimental Tests) facility at SLAC has been under Construction since summer 2010. Its goal is to produce ultrashort and transversely small bunches of very high intensity (20kA peak current) to facilitate advanced acceleration experiments like PWFA and DLA. In June of 2011 the first electron beam was brought into the newly constructed bunch-compression chicane. Commissioning work included restarting the linac and damping ring, verifying hardware, establishing a good beam trajectory, verifying the optics of the chicane, commissioning diagnostic devices for transverse and longitudinal bunch size, and tuning up the beam size and bunch compression. Running a high-intensity beam through the linac without BNS damping and with large energy spread is a significant challenge. Optical aberrations as well as wakefields conspire to increase beam emittance and the bunch compression is quite sensitive to details of the beam energy and orbit, not unlike what will be encountered in a linear-collider final-focusing system. In this paper we outline the steps we took while commissioning as well as the challenges encountered and how they were overcome.
 
slides icon Slides MOOAB03 [9.167 MB]  
 
WEPPP010 FACET: SLAC's New User Facility 2741
 
  • C.I. Clarke, F.-J. Decker, R.J. England, R.A. Erickson, C. Hast, M.J. Hogan, S.Z. Li, M.D. Litos, Y. Nosochkov, J.T. Seeman, J. Sheppard, U. Wienands, M. Woodley, G. Yocky
    SLAC, Menlo Park, California, USA
 
  Funding: Work supported by the U.S. Department of Energy under contract number DE-AC02-76SF00515.
FACET (Facility for Advanced Accelerator Experimental Tests) is a new User Facility at SLAC National Accelerator Laboratory. The first User Run started in spring 2012 with 20 GeV, 3 nC electron beams. The facility is designed to provide short (20 um) bunches and small (20 um wide) spot sizes, producing uniquely high power beams. FACET supports studies from many fields but in particular those of Plasma Wakefield Acceleration and Dielectric Wakefield Acceleration. The creation of drive and witness bunches and shaped bunch profiles is possible with "Notch" Collimation. FACET is also a source of THz radiation for material studies. Positrons will be available at FACET in future user runs. We present the User Facility and the available tools and opportunities for future experiments.
 
 
TUPPR088 Baseline Design of the SuperB Factory Injection System 2032
 
  • S. Guiducci, A. Bacci, M.E. Biagini, R. Boni, M. Boscolo, D. Pellegrini, M.A. Preger, P. Raimondi, A.R. Rossi, M. Zobov
    INFN/LNF, Frascati (Roma), Italy
  • M.A. Baylac
    LPSC, Grenoble, France
  • J. Brossard, S. Cavalier, O. Dadoun, T. Demma, P. Lepercq, E. Ngo Mandag, C. Rimbault, A. Variola
    LAL, Orsay, France
  • J.T. Seeman
    SLAC, Menlo Park, California, USA
  • D.N. Shatilov
    BINP SB RAS, Novosibirsk, Russia
 
  The injection complex of the SuperB, B-factory project of INFN consists of a polarized electron gun, a positron production system, electron and positron linac sections, a positron damping ring and the transfer lines connecting these systems and the collider main rings. To keep the ultra high luminosity nearly constant, continuous injection of 4 GeV electrons and 7 GeV positrons in both Low Energy Ring (LER) and High Energy Ring (HER) is necessary. In this paper we describe the baseline design and the beam dynamics studies performed to evaluate the system performance.