WEPPD039 Status of the Utility System Construction for the 3 GeV TPS Storage Ring 2597
 
  • J.-C. Chang, W.S. Chan, J.-R. Chen, Y.F. Chiu, Y.-C. Chung, K.C. Kuo, Y.-C. Lin, C.Y. Liu, I. Liu, Z.-D. Tsai, T.-S. Ueng
    NSRRC, Hsinchu, Taiwan
 
  The construction of the utility system for the 3.0 GeV Taiwan Photon Source (TPS) was started in the end of 2009. The utility building for the TPS ring will be completed in the end of 2011. The whole construction of the utility system is scheduled to be completed in the end of 2012. Total budget of this construction is about four million dollars. This utility system presented in this paper includes the electrical power, cooling water, air conditioning, compressed air and fire control systems.