Author: Chang, Y.-T.
Paper Title Page
WEPGF019 Database Applications Development of the TPS Control System 732
 
  • Y.-S. Cheng, Y.-T. Chang, J. Chen, P.C. Chiu, K.T. Hsu, C. H. Huang, C.Y. Liao
    NSRRC, Hsinchu, Taiwan
 
  The control system had been established for the new 3 GeV synchrotron light source (Taiwan Photon Source, TPS) which was successful to commission at December 2014. Various control system platforms with the EPICS framework had been implemented and commissioned. The relational database (RDB) has been set up for some of the TPS control system applications used. The EPICS data archive systems are necessary to be built to record various machine parameters and status information into the RDB for long time logging. The specific applications have been developed to analyze the archived data which retrieved from the RDB. One EPICS alarm system is necessary to be set up to monitor sub-system status and record detail information into the RDB if the problem happened. Some Web-based applications with RDB have been gradually created to show the TPS machine status related information. The efforts are described at this paper.  
poster icon Poster WEPGF019 [4.008 MB]  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
FRB3O01 Commissioning of the TPS Control System 1173
 
  • C.Y. Liao, Y.-T. Chang, J. Chen, Y.-S. Cheng, P.C. Chiu, K.T. Hsu, S.Y. Hsu, K.H. Hu, C. H. Huang, C.H. Kuo, D. Lee, C.-J. Wang, C.Y. Wu
    NSRRC, Hsinchu, Taiwan
 
  Control system for the Taiwan Photon Source (TPS) has been completed in 2014. Commissioning of the accelerator system is in proceeding. Electron beam were stored at the storage ring and emit first light in December 31, 2014. TPS control system adopts EPICS toolkits as its frameworks. The subsystems control interfaces include event based timing system, Ethernet based power supply control, corrector power supply control, PLC-based pulse magnet power supply control and machine protection system, insertion devices motion control system, various diagnostics related control environment, and etc. The standard hardware components had been installed and integrated, and the various IOCs (Input Output Controller) had been implemented as various subsystems control platforms. Low level and high level hardware and software are tested intensively in 2014 and final revise to prepare for routine operation is under way. Efforts will be summarized at this paper.  
slides icon Slides FRB3O01 [41.594 MB]  