Paper | Title | Page |
---|---|---|
MOP243 | Experimental Results of Beam Halo at IHEP | 151 |
|
||
Space-charge forces acting in mismatched beams have been identified as a major cause of beam halo. In this paper, we describe the beam halo experimental results in a FODO beam line at IHEP. With this beam transport line, experiments are firstly carried out to determine the main beam parameters at the exit of a RFQ with intense beams, and then the measured beam profiles at different positions are compared with the multi-particle simulation profiles to study the formation of beam halo. The maximum measured amplitudes of the matched and mismatched beam profiles agreed well with simulations. Details of the experiment will be presented. | ||
TUO3B04 | End to End Beam Dynamics and Design Optimization for CSNS Linac | 286 |
|
||
The China Spallation Neutron Source (CSNS) will use a linear accelerator delivering a 15mA beam up to 80MeV for injection into a rapid cycling synchrotron (RCS). Since each section of the linac was determined individually, a global optimization based on end-to-end simulation results has refined some design choices, including the drift-tube linac (DTL) and the medium energy beam transport (MEBT). The simulation results and reasons for adjustments are presented in this paper. | ||
![]() |
Slides TUO3B04 [1.131 MB] | |
TUO3C05 | Beam Commissioning Plan for CSNS Accelerators | 334 |
|
||
Funding: Supported by National Natural Science Foundation of China (11175193) The China Spallation Neutron Source (CSNS) is now under construction, and the beam commissioning of ion source will start from the end of 2013, and will last several years for whole accelerator. The commissioning plan for CSNS accelerators will be presented in the presentation, including the commissioning correlated parameters, the goal at different commissioning stages and some key commissioning procedures for each part of accelerators. The detailed schedule for commissioning will be also given. |
||
![]() |
Slides TUO3C05 [3.574 MB] | |