The Facility for Antiproton and Ion Research (FAIR) is a large scale multi project comprising 10 subprojects in the field of accelerators (pLINAC, SIS100, SuperFRS, p-bar, CR, HESR), experiments (CBM, APPA, NUSTAR, PANDA) and civil construction. This contribution describes the fundamental revamp of FAIR integrated project planning. Main objective is to preserve the advantages of a bottom-up planning topology with the actual and detailed level of information keeping the ~400 work package leader's central role as plan owners in their field of responsibility. Simultaneously different project phases (e.g. civil construction, procurement, installation, commissioning) need to be excluded from detailed plans while being re-integrated in the level-1 project master schedule. Additional cost profiles and resource assignment by name allow a progress tracking and flexible project steering.
|
|