Author: Lee, J.
Paper Title Page
WEB02 Beam Operation of the PAL-XFEL Injector Test Facility 615
 
  • J.H. Han, S.Y. Baek, M.S. Chae, H. J. Choi, T. Ha, J.H. Hong, J. Hu, W.H. Hwang, S.H. Jung, H.-S. Kang, C. Kim, C.H. Kim, I.Y. Kim, J.M. Kim, S.H. Kim, I.S. Ko, H.-S. Lee, J. Lee, S.J. Lee, W.W. Lee, C.-K. Min, G. Mun, D.H. Na, S.S. Park, S.J. Park, Y.J. Park, Y.G. Son, H. Yang
    PAL, Pohang, Kyungbuk, Republic of Korea
 
  The Pohang Accelerator Laboratory X-ray Free electron Laser (PAL-XFEL) project was launched in 2011. This project aims at the generation of X-ray FEL radiation in a range of 0.1 to 10 nm for photon users with a bunch repetition rate of 60 Hz. The machine consists of a 10 GeV normal conducting S-band linear accelerator and five undulator beamlines. The linac and two undulator beamlines will be constructed by the end of 2015 and first FEL radiation is expected in 2016. As a part of preparation for the project, an Injector Test Facility was constructed in 2012. Since December 2012, beam commissioning is being carried out to find optimum operating conditions and to test accelerator components including RF, laser, diagnostics, magnet, vacuum and control. We present the status of beam commissioning and components tests at the test facility.  
slides icon Slides WEB02 [10.249 MB]  
 
THP013 Slice Emittance Measurement using RF Deflecting Cavity at PAL-XFEL ITF 707
 
  • J. Lee
    POSTECH, Pohang, Kyungbuk, Republic of Korea
  • J.H. Han, J.H. Hong, I.S. Ko, S.J. Park
    PAL, Pohang, Kyungbuk, Republic of Korea
 
  One of key characteristic for operating PAL-XFEL is the time-dependent transverse properties of a bunch, slice emittance. To achieve the design FEL performance of PAL-XFEL a slice emittance of 0.4 mm mrad at 0.2 nC is required. An Injector Test Facility (ITF) was constructed to study beam properties. In addition to projected emittance measurement, slice emittance measurement is being done using a transverse RF deflecting cavity. We presents results of slice emittance measurement at ITF and future plan for the optimization of operating condition.