Paper | Title | Page |
---|---|---|
TUPAK015 | The SARAF-LINAC Project 2018 Status | 994 |
|
||
SNRC and CEA collaborate to the upgrade of the SARAF accelerator to 5 mA CW 40 MeV deuteron and proton beams (Phase 2). CEA is in charge of the design, construction and commissioning of the MEBT line and the superconducting linac (SARAF-LINAC Project). The prototypes of the 176 MHz NC rebuncher, SC cavities, RF coupler and SC Solenoid-Package are under construction and their test stands construction or adaptation is in progress at Saclay. Meanwhile, the cryomodules and the global system just passed their Critical Design Reviews. This paper presents the status of the SARAF-LINAC Project at April 2018. | ||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2018-TUPAK015 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |