Paper | Title | Page |
---|---|---|
THPAL134 | Commissioning of the Prototype C75 Cavities in a CEBAF Cryomodule | 3961 |
|
||
Funding: Authored by Jefferson Science Associates, LLC under U.S. DOE Contract No. DE-AC05-06OR23177 Prototype cavities have been built at Jefferson Lab to increase the energy of future refurbished CEBAF cryomodules to 75 MeV in the most cost efficient way. Three such cavities, named "C75", have been built from ingot Nb material of different purity and have been processed and tested. The two better performing cavities have been assembled into a "cavity pair" and installed in the latest refurbished original CEBAF cryomodule. The cryomodule was installed and commissioned in CEBAF. The results from the commissioning of the C75 cavities, compared with the original CEBAF cavities, are presented in this article. The vertical test performance of the C75 cavities was preserved in the cryomodule with one of the cavities achieving the performance specification of an accelerating gradient of 19 MV/m with a quality factor of ~8×109 at 2.07 K. The performance in terms of microphonics and tuner operation was similar to that of original CEBAF cavities, as expected, and the high-order modes are properly damped. The quality factor of the two C75 cavities was the highest achieved in a CEBAF cryomodule, possibly due to the better magnetic flux expulsion of ingot Nb than standard fine-grain Nb. |
||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2018-THPAL134 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
THPAL137 | Acceptance Testing of the First Group of LCLS II Cryomodules at Jefferson Lab | 3965 |
|
||
Funding: This work was supported by the LCLS-II Project and the US Department of Energy, Contract DE-AC02-76SF00515. The Thomas Jefferson National Accelerator Facility is currently engaged, along with several other Department of Energy (DOE) national laboratories, The Thomas Jefferson National Accelerator Facility is currently engaged, along with several other Department of Energy (DOE) national laboratories, in the Linac Co-herent Light Source II project (LCLS II). The SRF Insti-tute at Jefferson Lab is currently building 17 cryomod-ules for this project. The cryomodules are TESLA style cryomodules that have been modified for continuous wave (CW) operation and for other LCLS II specifica-tions. Each cryomodule contains eight 9-cell cavities with coaxial power couplers operating at 1.3 GHz. The cryomodules also contains a magnet package that con-sists of a quadrupole and two correctors. These cryomod-ules will be tested in the Cryomodule Test Facility (CMTF) at Jefferson Lab before shipment to the Stanford Linear Accelerator (SLAC). Acceptance testing of the LCLS II cryomodules began in December 2016. Seven cryomodules have currently completed Acceptance test-ing. This paper will summarize the results of those tests. |
||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2018-THPAL137 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |
THPAL141 | Optimizing Procurement Strategies for LCLS-II | 3972 |
|
||
Funding: This work was supported by the LCLS-II Project and the U.S. Department of Energy, Contract DE-AC02-76SF00515 The SLAC National Accelerator Laboratory is currently constructing a major upgrade to its accelerator, the Linac Coherent Light Source II (LCLS-II). Several Department of Energy national laboratories, including the Thomas Jefferson National Accelerator Facility (JLab), are participating in this project. JLab is responsible for procuring a number of critical components. Over the course of this project, JLab has evolved several procurement strategies to minimize risk and improve performance while working within the constraints of budget and schedule. This paper discusses the impact of procurement choices on project technical success. |
||
DOI • | reference for this paper ※ https://doi.org/10.18429/JACoW-IPAC2018-THPAL141 | |
Export • | reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml) | |