Author: Yin, Z.G.
Paper Title Page
TUP005 Three Years Operation of CYCIAE-100 156
 
  • T. Ge, L.C. Cao, Z.H. Fu, S.G. Hou, B. Ji, H. Jiang, S.Q. Li, Y.Q. Li, Z.W. Liu, Y.L. Lv, G.F. Pan, L. Wang, L.P. Wen, Z.G. Yin, T.J. Zhang
    CIAE, Beijing, People’s Republic of China
 
  The 100 MeV high intensity proton cyclotron (CYCIAE-100) developed by China Institute of Atomic Energy is a multi-purpose variable energy AVF cyclotron. Its design specifications are: energy from 75 to 100 MeV continuously adjustable, beam intensity 200uA, beam current can be extracted in both directions. CYCIAE-100 was commissioned to extract 100 MeV proton beam for the first time in July 2014. The first physics experiment was carried out in November 2016. By June 2019, the design specifications of CYCIAE-100 was commissioned and the maximum beam power was 52 kW. The beam intensity range from 1 pA to 520 µA is achieved, and the beam stability is about 1% for 8 hours. Several typical physics experiments have been carried out. Such as: The physics experiment of CYCIAE-100 driving ISOL device to generate radioactive nuclear beam, SiC and SRAM proton irradiation experiments, calibration experiment of high-energy proton electron total dose detector probe, etc. At present, the beam time for CYCIAE-100 is about 5,000 hours, providing effective beam time for more than 3,000 hours for many users at home and abroad, and the other beam time for beam development.  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-Cyclotrons2019-TUP005  
About • paper received ※ 15 September 2019       paper accepted ※ 26 September 2019       issue date ※ 20 June 2020  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)  
 
FRA01 A New Solution for Cost Effective, High Average Power (2 GeV, 6 MW) Proton Accelerator and its R&D Activities 334
 
  • T.J. Zhang, S. An, T.J. Bian, F.P. Guan, M. Li, S. Pei, C. Wang, F. Wang, Z.G. Yin
    CIAE, Beijing, People’s Republic of China
 
  The 100 MeV compact cyclotron, CYCIAE-100 was approved to start the construction in 2011, and the first proton beam was extracted on July 4, 2014. In 2017, the 200 µA proton beam development was conducted, and in 2018, the production of high power beam from 20 kW to 52 kW had been delivered successfully to the beam dump. Due to the successful construction of 435 tons magnet for CYCIAE-100, it has been proved that the gradient adjustment of magnetic field along radius can effectively enhance the vertical focusing during the isochronous acceleration. This key technology was applied to the general design of a 2 GeV CW proton accelerator, the energy limitation of the isochronous machine is increased from ~1 GeV to 2 GeV, by our contribution of the beam dynamics study for high energy isochronous FFAG. This paper will introduce CIAE’s engineering experience of precision magnet, high power RF systems, and the advantages of beam dynamics simulation based on large-scale parallel computing. The cost-effective solution for such a 2 GeV high power circular accelerator complex will be presented in detail after the brief introduction about the high power proton beam production by the CYCIAE-100.  
slides icon Slides FRA01 [19.669 MB]  
DOI • reference for this paper ※ https://doi.org/10.18429/JACoW-Cyclotrons2019-FRA01  
About • paper received ※ 15 September 2019       paper accepted ※ 23 June 2020       issue date ※ 20 June 2020  
Export • reference for this paper using ※ BibTeX, ※ LaTeX, ※ Text/Word, ※ RIS, ※ EndNote (xml)